Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-022On track5ApprovalStage-Gate

Remote Video Hearings Roll-out — Makkah Region

Add to watchlist

Equip 180 courtrooms and circuit offices in Jeddah, Makkah and Taif for video hearings with secure recording.

Budget (BAC)

SAR 46M

Actual cost

SAR 920K

⁦2%⁩ of budget

Progress

⁦2%⁩

Planned ⁦2%⁩

Estimate at completion

SAR 46M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-03-31⁩

On baseline

ApprovalPhase ⁦5⁩ of ⁦11⁩

Next gate:Procurement20 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate13 February 2026Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate2 August 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate1 September 2026Approval · Current phaseApproval · Current phase
  6. Gate into «Procurement»DecisionNot held yetDate20 September 2026Procurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

0Achieved
3On track
2At risk
0Late
Average delay18 days
Jan 27Apr 27Jul 27Oct 27Jan 28Apr 28
Contractual
Build completePlanned: ⁦2027-08-03⁩Forecast / actual: ⁦2027-08-21⁩Delay: 18 daysG3 +18
Executive
Project plan approvedPlanned: ⁦2026-12-05⁩Forecast / actual: ⁦2027-01-08⁩Delay: 34 daysG1 +34
Payment
Final handoverPlanned: ⁦2028-03-31⁩Forecast / actual: ⁦2028-04-02⁩Delay: 2 daysG5 +2
Regulatory
Testing & acceptance completePlanned: ⁦2027-12-26⁩Forecast / actual: ⁦2028-01-03⁩Delay: 8 daysG4 +8
Project
Designs approvedPlanned: ⁦2027-03-12⁩Forecast / actual: ⁦2027-04-08⁩Delay: 27 daysG2 +27

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-12-05⁩⁦2027-01-08⁩⁦+34⁩ daysEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.saAt risk0Not requested
Designs approvedMS-G2Project⁦2027-03-12⁩⁦2027-04-08⁩⁦+27⁩ daysEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.saAt risk0Not requested
Build completeMS-G3Contractual⁦2027-08-03⁩⁦2027-08-21⁩⁦+18⁩ daysEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.saOn track0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2027-12-26⁩⁦2028-01-03⁩⁦+8⁩ daysEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.saOn track0Not requested
Final handoverMS-G5Payment⁦2028-03-31⁩⁦2028-04-02⁩⁦+2⁩ daysEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.saOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline022-D1SubmittedEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-10-18⁩V1⁦1⁩ of ⁦2⁩
Deliverable: Monitoring & reporting022-D2DraftEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-12-05⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Detailed design022-D3DraftEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saEng. Bandar M. Al-Shammari⁦2027-01-22⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Permits & approvals022-D4DraftEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.saEng. Bandar M. Al-Shammari⁦2027-03-12⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Site works & excavation022-D5DraftEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.saEng. Bandar M. Al-Shammari⁦2027-04-29⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Structure022-D6DraftEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.saEng. Bandar M. Al-Shammari⁦2027-06-16⁩V0⁦0⁩ of ⁦2⁩
⁦1⁩–⁦6⁩ of ⁦6⁩