Remote Video Hearings Roll-out — Makkah Region
Add to watchlistEquip 180 courtrooms and circuit offices in Jeddah, Makkah and Taif for video hearings with secure recording.
Budget (BAC)
Actual cost
2% of budget
Progress
Planned 2%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ApprovalPhase 5 of 11
Next gate:Procurement20 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionConditional goDate13 February 2026Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 August 2026Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate1 September 2026Approval · Current phaseApproval · Current phase
- Gate into «Procurement»DecisionNot held yetDate20 September 2026Procurement · Not startedProcurement · Not started
- Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-12-05 | 2027-01-08 | +34 days | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.sa | At risk | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-03-12 | 2027-04-08 | +27 days | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.sa | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2027-08-03 | 2027-08-21 | +18 days | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.sa | On track | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-12-26 | 2028-01-03 | +8 days | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.sa | On track | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2028-03-31 | 2028-04-02 | +2 days | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline022-D1 | Submitted | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2026-10-18 | V1 | 1 of 2 |
| Deliverable: Monitoring & reporting022-D2 | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2026-12-05 | V0 | 0 of 2 |
| Deliverable: Detailed design022-D3 | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2027-01-22 | V0 | 0 of 2 |
| Deliverable: Permits & approvals022-D4 | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2027-03-12 | V0 | 0 of 2 |
| Deliverable: Site works & excavation022-D5 | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2027-04-29 | V0 | 0 of 2 |
| Deliverable: Structure022-D6 | Draft | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2027-06-16 | V0 | 0 of 2 |