Asir Administrative Court of Appeal Complex
Add to watchlistA 120,000 m² complex for the administrative court of appeal serving Asir, Jazan, Najran and Al-Baha.
Budget (BAC)
Actual cost
2% of budget
Progress
Planned 2%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ProcurementPhase 6 of 11
Next gate:Execution12 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate17 October 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 April 2026Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate25 May 2026Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate24 June 2026Procurement · Current phaseProcurement · Current phase
- Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Closure readiness
Closure planned after the forecast finish on 2028-12-31
A preview of what closure will need, with the planned dates, and the lessons captured so far.
Closure checklist
Seven mandatory items before any project closes.
- 1
Deliverables acceptedNot started
Final acceptance of every deliverable
Eng. Bandar M. Al-ShammariPlanned 2028-12-21
- 2
Financial closureNot started
Spend reconciled, commitments closed
Khalid N. Al-MutairiPlanned 2029-01-20
- 3
Contract closureNot started
Contracts closed, retention released
Khalid N. Al-MutairiPlanned 2029-01-30
- 4
Documents archivedNot started
Documents archived with classification
Eng. Ibrahim A. Al-GhamdiPlanned 2029-01-25
- 5
Lessons learnedNot started
Lessons-learned session
Eng. Ibrahim A. Al-GhamdiPlanned 2029-01-15
- 6
Benefits owner assignedNot started
Benefits handed to their owner with a measurement plan
Eng. Bandar M. Al-ShammariPlanned 2029-01-10
- 7
Final report approvedNot started
Final report and its approval
Eng. Ibrahim A. Al-GhamdiPlanned 2029-02-04
Post-implementation review
Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?
The review comes after closure
About three months after the forecast finish (2028-12-31), with the sponsor and the benefits owner.
Lessons learned
0 lessons — offered automatically to similar projects when they are created.
No lessons captured yet
Capture what the team learned during delivery; closure needs at least one.
Benefits handover
Each benefit moves from the project manager to an owner who measures it after closure.
No benefits recorded for this project.