Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-021On track6ProcurementConstruction

Asir Administrative Court of Appeal Complex

Add to watchlist

A 120,000 m² complex for the administrative court of appeal serving Asir, Jazan, Najran and Al-Baha.

Budget (BAC)

SAR 520M

Actual cost

SAR 10.4M

⁦2%⁩ of budget

Progress

⁦2%⁩

Planned ⁦2%⁩

Estimate at completion

SAR 520M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

ProcurementPhase ⁦6⁩ of ⁦11⁩

Next gate:Execution12 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate17 October 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate5 April 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate25 May 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate24 June 2026Procurement · Current phaseProcurement · Current phase
  7. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Closure readiness

Closure planned after the forecast finish on ⁦2028-12-31⁩

A preview of what closure will need, with the planned dates, and the lessons captured so far.

0/7

Closure checklist

Seven mandatory items before any project closes.

  1. 1

    Deliverables acceptedNot started

    Final acceptance of every deliverable

    Eng. Bandar M. Al-ShammariPlanned ⁦2028-12-21⁩

  2. 2

    Financial closureNot started

    Spend reconciled, commitments closed

    Khalid N. Al-MutairiPlanned ⁦2029-01-20⁩

  3. 3

    Contract closureNot started

    Contracts closed, retention released

    Khalid N. Al-MutairiPlanned ⁦2029-01-30⁩

  4. 4

    Documents archivedNot started

    Documents archived with classification

    Eng. Ibrahim A. Al-GhamdiPlanned ⁦2029-01-25⁩

  5. 5

    Lessons learnedNot started

    Lessons-learned session

    Eng. Ibrahim A. Al-GhamdiPlanned ⁦2029-01-15⁩

  6. 6

    Benefits owner assignedNot started

    Benefits handed to their owner with a measurement plan

    Eng. Bandar M. Al-ShammariPlanned ⁦2029-01-10⁩

  7. 7

    Final report approvedNot started

    Final report and its approval

    Eng. Ibrahim A. Al-GhamdiPlanned ⁦2029-02-04⁩

Post-implementation review

Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?

The review comes after closure

About three months after the forecast finish (⁦2028-12-31⁩), with the sponsor and the benefits owner.

Lessons learned

0 lessons — offered automatically to similar projects when they are created.

Knowledge base

No lessons captured yet

Capture what the team learned during delivery; closure needs at least one.

Benefits handover

Each benefit moves from the project manager to an owner who measures it after closure.

No benefits recorded for this project.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close