PRJ-2026-021On track6ProcurementConstruction

Asir Administrative Court of Appeal Complex

Add to watchlist

A 120,000 m² complex for the administrative court of appeal serving Asir, Jazan, Najran and Al-Baha.

Budget (BAC)

SAR 520M

Actual cost

SAR 10.4M

⁦2%⁩ of budget

Progress

⁦2%⁩

Planned ⁦2%⁩

Estimate at completion

SAR 520M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

ProcurementPhase ⁦6⁩ of ⁦11⁩

Next gate:Execution12 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate17 October 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate5 April 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate25 May 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate24 June 2026Procurement · Current phaseProcurement · Current phase
  7. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

0Achieved
1On track
4At risk
0Late
Average delay58 days
Oct 26Jan 27Apr 27Jul 27Oct 27Jan 28Apr 28Jul 28Oct 28Jan 29
Contractual
Build completePlanned: ⁦2027-11-30⁩Forecast / actual: ⁦2028-01-27⁩Delay: 58 daysG3 +58
Executive
Project plan approvedPlanned: ⁦2026-10-29⁩Forecast / actual: ⁦2027-02-16⁩Delay: 110 daysG1 +110
Payment
Final handoverPlanned: ⁦2028-12-31⁩Forecast / actual: ⁦2029-01-06⁩Delay: 6 daysG5 +6
Regulatory
Testing & acceptance completePlanned: ⁦2028-07-25⁩Forecast / actual: ⁦2028-08-21⁩Delay: 27 daysG4 +27
Project
Designs approvedPlanned: ⁦2027-04-05⁩Forecast / actual: ⁦2027-07-04⁩Delay: 90 daysG2 +90

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-10-29⁩⁦2027-02-16⁩⁦+110⁩ daysEng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@bog.gov.saAt risk0Not requested
Designs approvedMS-G2Project⁦2027-04-05⁩⁦2027-07-04⁩⁦+90⁩ daysEng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@bog.gov.saAt risk0Not requested
Build completeMS-G3Contractual⁦2027-11-30⁩⁦2028-01-27⁩⁦+58⁩ daysEng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@bog.gov.saAt risk0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2028-07-25⁩⁦2028-08-21⁩⁦+27⁩ daysEng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@bog.gov.saAt risk0Not requested
Final handoverMS-G5Payment⁦2028-12-31⁩⁦2029-01-06⁩⁦+6⁩ daysEng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@bog.gov.saOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline021-D1SubmittedEng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-08-10⁩V1⁦1⁩ of ⁦2⁩
Deliverable: Monitoring & reporting021-D2DraftEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-10-29⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Detailed design021-D3DraftEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saEng. Bandar M. Al-Shammari⁦2027-01-16⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Permits & approvals021-D4DraftEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.saEng. Bandar M. Al-Shammari⁦2027-04-05⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Site works & excavation021-D5DraftEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.saEng. Bandar M. Al-Shammari⁦2027-06-24⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Structure021-D6DraftEng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@bog.gov.saEng. Bandar M. Al-Shammari⁦2027-09-11⁩V0⁦0⁩ of ⁦2⁩
⁦1⁩–⁦6⁩ of ⁦6⁩