Asir Administrative Court of Appeal Complex
Add to watchlistA 120,000 m² complex for the administrative court of appeal serving Asir, Jazan, Najran and Al-Baha.
Budget (BAC)
Actual cost
2% of budget
Progress
Planned 2%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ProcurementPhase 6 of 11
Next gate:Execution12 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate17 October 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 April 2026Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate25 May 2026Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate24 June 2026Procurement · Current phaseProcurement · Current phase
- Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-10-29 | 2027-02-16 | +110 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@bog.gov.sa | At risk | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-04-05 | 2027-07-04 | +90 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@bog.gov.sa | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2027-11-30 | 2028-01-27 | +58 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@bog.gov.sa | At risk | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2028-07-25 | 2028-08-21 | +27 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@bog.gov.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2028-12-31 | 2029-01-06 | +6 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@bog.gov.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline021-D1 | Submitted | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2026-08-10 | V1 | 1 of 2 |
| Deliverable: Monitoring & reporting021-D2 | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2026-10-29 | V0 | 0 of 2 |
| Deliverable: Detailed design021-D3 | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2027-01-16 | V0 | 0 of 2 |
| Deliverable: Permits & approvals021-D4 | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2027-04-05 | V0 | 0 of 2 |
| Deliverable: Site works & excavation021-D5 | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2027-06-24 | V0 | 0 of 2 |
| Deliverable: Structure021-D6 | Draft | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2027-09-11 | V0 | 0 of 2 |