PRJ-2026-021On track6ProcurementConstruction
Asir Administrative Court of Appeal Complex
Add to watchlistA 120,000 m² complex for the administrative court of appeal serving Asir, Jazan, Najran and Al-Baha.
Project managerEng. Ibrahim A. Al-GhamdiSponsorEng. Turki A. Al-AnaziProgrammeMajor Judicial Complexes Programme
Budget (BAC)
SAR 520M
Actual cost
SAR 10.4M
2% of budget
Progress
2%
Planned 2%
Estimate at completion
SAR 520M
SPI · CPI
1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Forecast finish
2028-12-31
On baseline
ProcurementPhase 6 of 11
Next gate:Execution12 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate17 October 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 April 2026Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate25 May 2026Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate24 June 2026Procurement · Current phaseProcurement · Current phase
- Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started