PRJ-2026-021On track6ProcurementConstruction

Asir Administrative Court of Appeal Complex

Add to watchlist

A 120,000 m² complex for the administrative court of appeal serving Asir, Jazan, Najran and Al-Baha.

Budget (BAC)

SAR 520M

Actual cost

SAR 10.4M

⁦2%⁩ of budget

Progress

⁦2%⁩

Planned ⁦2%⁩

Estimate at completion

SAR 520M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

ProcurementPhase ⁦6⁩ of ⁦11⁩

Next gate:Execution12 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate17 October 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate5 April 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate25 May 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate24 June 2026Procurement · Current phaseProcurement · Current phase
  7. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started