Asir Administrative Court of Appeal Complex
Add to watchlistA 120,000 m² complex for the administrative court of appeal serving Asir, Jazan, Najran and Al-Baha.
Budget (BAC)
Actual cost
2% of budget
Progress
Planned 2%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ProcurementPhase 6 of 11
Next gate:Execution12 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate17 October 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 April 2026Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate25 May 2026Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate24 June 2026Procurement · Current phaseProcurement · Current phase
- Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Project lifecycle and its gates
Current phase: Procurement. Pick a gate on the track to review it.
- Gate into «Feasibility»DecisionGoDate17 October 2025All criteria and required documents met.IdeaComplete
- Gate into «Initiation»DecisionGoDate4 February 2026All criteria and required documents met.FeasibilityComplete
- Gate into «Planning»DecisionGoDate5 April 2026All criteria and required documents met.InitiationComplete
- Gate into «Approval»DecisionGoDate25 May 2026All criteria and required documents met.PlanningComplete
- Gate into «Procurement»DecisionGoDate24 June 2026All criteria and required documents met.ApprovalComplete
- Gate into «Execution»DecisionNot held yetDate12 September 2026ProcurementCurrent phaseCurrent phase
- Gate into «Monitoring & Control»DecisionNot held yet7ExecutionNot started
- Gate into «Handover»DecisionNot held yet8Monitoring & ControlNot started
- Gate into «Closure»DecisionNot held yet9HandoverNot started
- Gate into «Benefits Realization»DecisionNot held yet10ClosureNot started
- 11Benefits RealizationNot started
Award gate — into execution
Gate readiness
Meets the pass mark
Automated control: no move until the criteria are met
- 1 mandatory checklist item open
- 1 required document not approved
- 1 mandatory criterion under 70 points
Checklist
3 of 4 done
- Contract signed, guarantees lodgedMandatory
- Vendor detailed planMandatory
- Execution kick-off heldMandatory
- Post-award baseline approvedMandatory
Required documents
2 of 3 approved
- Signed contractApproved · V1
- Vendor planApproved · V1
- Kick-off minutesNot submitted
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Vendor and named-team readinessweight 35%Met
Awaiting evidence from the project team.
Post-award baseline approvedweight 35%Not met
Awaiting evidence from the project team.
Test and quality planweight 30%
Awaiting evidence from the project team.
Approvers
Bid Evaluation & Award Committee
- Munirah A. Al-KhalidiAward committee chairVote pending
- Eng. Turki A. Al-AnaziProject sponsorVote pending
- Dr. Noura M. Al-OtaibiEPMO directorVote pending