Original
Original baseline
- Finish
- 2028-12-31
- Budget
- SAR 520M
- 17 activities
Approved with the project plan at the planning gate.
Approved 2026-04-05 · by Eng. Turki A. Al-Anazi
A 120,000 m² complex for the administrative court of appeal serving Asir, Jazan, Najran and Al-Baha.
Budget (BAC)
Actual cost
2% of budget
Progress
Planned 2%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ProcurementPhase 6 of 11
Next gate:Execution12 September 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2026-04-05 · by Eng. Turki A. Al-Anazi
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Ibrahim A. Al-Ghamdi
What changed from version A to version B
Finish
2028-12-312029-01-06
+6 days
Budget
SAR 520MSAR 520M
0.00 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference