Administrative Correspondence & e-Archive Platform
Add to watchlistAutomated correspondence and e-archiving, linked to the government communications network.
Budget (BAC)
Actual cost
95% of budget
Progress
Planned 100%
Estimate at completion
SPI · CPI
Forecast finish
46 days behind baseline
HandoverPhase 9 of 11
Next gate:Closure30 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate2 August 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate19 February 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate10 March 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate28 April 2025Execution · CompleteExecution · Complete
- Gate into «Monitoring & Control»DecisionGoDate5 July 2026Monitoring & Control · CompleteMonitoring & Control · Complete
- Gate into «Handover»DecisionGoDate11 August 2026Handover · Current phaseHandover · Current phase
- Gate into «Closure»DecisionNot held yetDate30 September 2026Closure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+85 days vs approved
- Critical activities
- 2
- of 2 open activities
- Late activities
- 1
- past their baseline finish
- Schedule performance
- 0.95
- earned ÷ planned value
- Next milestone
- in 57 days
- Final handover
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
22 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 2 open activities, data date 2026-10-28
“Go-live & handover” needs a pace 4.0× faster than it has kept
It earned 33% in 113 days; the forecast assumes the rest in 57 days. At the pace so far it finishes on 2027-06-14.
Milestones slip 55 days on average — and it is getting worse
Each milestone’s slip in days, in date order; the later ones slip more than the early ones.
The critical chain
In date order, to final acceptance