Case & Judgment Archive Digitisation
Add to watchlistScan 4.2 million pages of paper case files and judgments, index them automatically and link them to the case records in Mueen.
Budget (BAC)
Actual cost
6% of budget
Progress
Planned 6%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
PlanningPhase 4 of 11
Next gate:Approval1 August 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate16 January 2026Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 July 2026Planning · Current phasePlanning · Current phase
- Gate into «Approval»DecisionNot held yetDate1 August 2026Approval · Not startedApproval · Not started
- Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
- Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+5 days vs approved
- Critical activities
- 11
- of 15 open activities
- Late activities
- 10
- past their baseline finish
- Schedule performance
- 0.48
- earned ÷ planned value
- Next milestone
- in 37 days
- Project plan approved
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
22 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 15 open activities, data date 2026-10-28
“Monitoring & reporting” needs a pace 1.8× faster than it has kept
It earned 50% in 68 days; the forecast assumes the rest in 37 days. At the pace so far it finishes on 2027-01-04.
The critical chain
In date order, to final acceptance