Case & Judgment Archive Digitisation

Add to watchlist

Scan 4.2 million pages of paper case files and judgments, index them automatically and link them to the case records in Mueen.

Budget (BAC)

SAR 24M

Actual cost

SAR 1.4M

⁦6%⁩ of budget

Progress

⁦6%⁩

Planned ⁦6%⁩

Estimate at completion

SAR 24M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-30⁩

On baseline

PlanningPhase ⁦4⁩ of ⁦11⁩

Next gate:Approval1 August 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate16 January 2026Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate5 July 2026Planning · Current phasePlanning · Current phase
  5. Gate into «Approval»DecisionNot held yetDate1 August 2026Approval · Not startedApproval · Not started
  6. Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+5⁩ days vs approved

Original baseline⁦2027-12-30⁩
Approved baseline⁦2027-12-30⁩
Current forecast⁦2028-01-04⁩
By earned schedule⁦2028-10-03⁩
Critical activities
11
of ⁦15⁩ open activities
Late activities
10
past their baseline finish
Schedule performance
0.48
earned ÷ planned value
Next milestone
in 37 days
Project plan approved
Expand allCollapse all
Activity
Case & Judgment Archive DigitisationPlanned: ⁦2026-07-05⁩ → ⁦2027-12-30⁩Forecast: ⁦2026-07-05⁩ → ⁦2028-01-04⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2026-07-05⁩ → ⁦2026-11-04⁩Forecast: ⁦2026-07-05⁩ → ⁦2026-12-04⁩Float: ⁦0⁩d
Project plan & baselinePlanned: ⁦2026-07-05⁩ → ⁦2026-09-18⁩Actual: ⁦2026-07-05⁩ → ⁦2026-10-26⁩
Monitoring & reportingPlanned: ⁦2026-08-21⁩ → ⁦2026-11-04⁩Forecast: ⁦2026-08-21⁩ → ⁦2026-12-04⁩Float: ⁦0⁩d+30
Project plan approvedPlanned: ⁦2026-11-04⁩ → ⁦2026-11-04⁩Forecast: ⁦2026-12-04⁩ → ⁦2026-12-04⁩Float: ⁦396⁩dProject plan approved
Analysis & designPlanned: ⁦2026-10-07⁩ → ⁦2027-02-05⁩Forecast: ⁦2026-11-08⁩ → ⁦2027-03-02⁩Float: ⁦0⁩d
Business requirementsPlanned: ⁦2026-10-07⁩ → ⁦2026-12-21⁩Forecast: ⁦2026-11-08⁩ → ⁦2027-01-17⁩Float: ⁦0⁩d+27
Solution designPlanned: ⁦2026-11-22⁩ → ⁦2027-02-05⁩Forecast: ⁦2026-12-22⁩ → ⁦2027-03-02⁩Float: ⁦0⁩d+25
Designs approvedPlanned: ⁦2027-02-05⁩ → ⁦2027-02-05⁩Forecast: ⁦2027-03-02⁩ → ⁦2027-03-02⁩Float: ⁦308⁩dDesigns approved
BuildPlanned: ⁦2027-01-08⁩ → ⁦2027-06-26⁩Forecast: ⁦2027-02-04⁩ → ⁦2027-07-12⁩Float: ⁦0⁩d
Release 1Planned: ⁦2027-01-08⁩ → ⁦2027-03-24⁩Forecast: ⁦2027-02-04⁩ → ⁦2027-04-15⁩Float: ⁦0⁩d+22
Release 2Planned: ⁦2027-02-24⁩ → ⁦2027-05-10⁩Forecast: ⁦2027-03-20⁩ → ⁦2027-05-29⁩Float: ⁦0⁩d+19
IntegrationsPlanned: ⁦2027-04-12⁩ → ⁦2027-06-26⁩Forecast: ⁦2027-05-03⁩ → ⁦2027-07-12⁩Float: ⁦0⁩d+16
Build completePlanned: ⁦2027-06-26⁩ → ⁦2027-06-26⁩Forecast: ⁦2027-07-12⁩ → ⁦2027-07-12⁩Float: ⁦176⁩dBuild complete
Testing & acceptancePlanned: ⁦2027-05-29⁩ → ⁦2027-09-27⁩Forecast: ⁦2027-06-16⁩ → ⁦2027-10-08⁩Float: ⁦0⁩d
System testingPlanned: ⁦2027-05-29⁩ → ⁦2027-08-12⁩Forecast: ⁦2027-06-16⁩ → ⁦2027-08-25⁩Float: ⁦0⁩d+13
User acceptance testingPlanned: ⁦2027-07-14⁩ → ⁦2027-09-27⁩Forecast: ⁦2027-07-30⁩ → ⁦2027-10-08⁩Float: ⁦0⁩d+11
Testing & acceptance completePlanned: ⁦2027-09-27⁩ → ⁦2027-09-27⁩Forecast: ⁦2027-10-08⁩ → ⁦2027-10-08⁩Float: ⁦88⁩dTesting & acceptance complete
Launch & handoverPlanned: ⁦2027-08-30⁩ → ⁦2027-12-30⁩Forecast: ⁦2027-09-12⁩ → ⁦2028-01-04⁩Float: ⁦0⁩d
Training & changePlanned: ⁦2027-08-30⁩ → ⁦2027-11-13⁩Forecast: ⁦2027-09-12⁩ → ⁦2027-11-21⁩Float: ⁦0⁩d+8
Go-live & handoverPlanned: ⁦2027-10-16⁩ → ⁦2027-12-30⁩Forecast: ⁦2027-10-26⁩ → ⁦2028-01-04⁩Float: ⁦0⁩d+5
Final handoverPlanned: ⁦2027-12-30⁩ → ⁦2027-12-30⁩Forecast: ⁦2028-01-04⁩ → ⁦2028-01-04⁩Float: ⁦0⁩dFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦22⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦15⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦10⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Monitoring & reporting” needs a pace ⁦1.8⁩× faster than it has kept

It earned ⁦50%⁩ in 68 days; the forecast assumes the rest in 37 days. At the pace so far it finishes on ⁦2027-01-04⁩.

The critical chain

In date order, to final acceptance