Riyadh Administrative Court Building
Remove from watchlistA 92,000 m² building for 42 judicial circuits — ending nine leased premises and bringing beneficiary services under one roof.
Budget (BAC)
Actual cost
70% of budget
Progress
Planned 82%
Estimate at completion
SAR +140.5M
SPI · CPI
Forecast finish
152 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control4 August 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate18 August 2023Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate28 March 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate29 April 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate23 July 2024Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate4 August 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth