Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-007Critical7ExecutionConstruction

Riyadh Administrative Court Building

Remove from watchlist

A 92,000 m² building for 42 judicial circuits — ending nine leased premises and bringing beneficiary services under one roof.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 640M

Actual cost

SAR 444.9M

⁦70%⁩ of budget

Progress

⁦57%⁩

Planned ⁦82%⁩

Estimate at completion

SAR 780.5M

SAR +140.5M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control4 August 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate18 August 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate28 March 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate29 April 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate23 July 2024Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate4 August 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+153⁩ days vs approved

Original baseline⁦2026-12-31⁩
Approved baseline⁦2026-12-31⁩
Current forecast⁦2027-06-02⁩
By earned schedule⁦2029-02-06⁩
Critical activities
6
of ⁦7⁩ open activities
Late activities
5
past their baseline finish
Schedule performance
0.58
earned ÷ planned value
Next milestone
in 169 days
Testing & acceptance complete
Expand allCollapse all
Activity
Riyadh Administrative Court BuildingPlanned: ⁦2024-02-04⁩ → ⁦2026-12-31⁩Forecast: ⁦2024-02-04⁩ → ⁦2027-06-02⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2024-02-04⁩ → ⁦2024-09-10⁩Actual: ⁦2024-02-04⁩ → ⁦2025-01-10⁩
Project plan & baselinePlanned: ⁦2024-02-04⁩ → ⁦2024-06-18⁩Actual: ⁦2024-02-04⁩ → ⁦2024-09-01⁩
Monitoring & reportingPlanned: ⁦2024-04-28⁩ → ⁦2024-09-10⁩Actual: ⁦2024-06-14⁩ → ⁦2025-01-10⁩
Project plan approvedPlanned: ⁦2024-09-10⁩ → ⁦2024-09-10⁩Actual: ⁦2025-01-10⁩ → ⁦2025-01-10⁩Project plan approved
Design & permitsPlanned: ⁦2024-07-21⁩ → ⁦2025-02-25⁩Actual: ⁦2024-10-23⁩ → ⁦2025-09-29⁩
Detailed designPlanned: ⁦2024-07-21⁩ → ⁦2024-12-03⁩Actual: ⁦2024-10-23⁩ → ⁦2025-05-21⁩
Permits & approvalsPlanned: ⁦2024-10-14⁩ → ⁦2025-02-25⁩Actual: ⁦2025-03-04⁩ → ⁦2025-09-29⁩
Designs approvedPlanned: ⁦2025-02-25⁩ → ⁦2025-02-25⁩Actual: ⁦2025-09-29⁩ → ⁦2025-09-29⁩Designs approved
Civil worksPlanned: ⁦2025-01-06⁩ → ⁦2025-11-05⁩Actual: ⁦2025-07-13⁩ → ⁦2026-10-26⁩
Site works & excavationPlanned: ⁦2025-01-06⁩ → ⁦2025-05-21⁩Actual: ⁦2025-07-13⁩ → ⁦2026-02-08⁩
StructurePlanned: ⁦2025-03-31⁩ → ⁦2025-08-13⁩Actual: ⁦2025-11-21⁩ → ⁦2026-06-19⁩
FinishesPlanned: ⁦2025-06-23⁩ → ⁦2025-11-05⁩Actual: ⁦2026-04-01⁩ → ⁦2026-10-26⁩
Build completePlanned: ⁦2025-11-05⁩ → ⁦2025-11-05⁩Actual: ⁦2026-10-26⁩ → ⁦2026-10-26⁩Build complete
MEP worksPlanned: ⁦2025-09-15⁩ → ⁦2026-07-16⁩Forecast: ⁦2025-09-15⁩ → ⁦2027-04-15⁩Float: ⁦0⁩d
SupplyPlanned: ⁦2025-09-15⁩ → ⁦2026-01-28⁩Forecast: ⁦2025-09-15⁩ → ⁦2027-02-26⁩Float: ⁦0⁩d+394
InstallationPlanned: ⁦2025-12-09⁩ → ⁦2026-04-22⁩Forecast: ⁦2027-02-12⁩ → ⁦2027-03-22⁩Float: ⁦0⁩d+334
Testing & commissioningPlanned: ⁦2026-03-03⁩ → ⁦2026-07-16⁩Forecast: ⁦2027-03-08⁩ → ⁦2027-04-15⁩Float: ⁦0⁩d+273
Testing & acceptance completePlanned: ⁦2026-07-16⁩ → ⁦2026-07-16⁩Forecast: ⁦2027-04-15⁩ → ⁦2027-04-15⁩Float: ⁦48⁩dTesting & acceptance complete
HandoverPlanned: ⁦2026-05-26⁩ → ⁦2026-12-31⁩Forecast: ⁦2027-04-01⁩ → ⁦2027-06-02⁩Float: ⁦0⁩d
Provisional acceptancePlanned: ⁦2026-05-26⁩ → ⁦2026-10-08⁩Forecast: ⁦2027-04-01⁩ → ⁦2027-05-09⁩Float: ⁦0⁩d+213
Final acceptancePlanned: ⁦2026-08-18⁩ → ⁦2026-12-31⁩Forecast: ⁦2027-04-25⁩ → ⁦2027-06-02⁩Float: ⁦0⁩d+153
Final handoverPlanned: ⁦2026-12-31⁩ → ⁦2026-12-31⁩Forecast: ⁦2027-06-02⁩ → ⁦2027-06-02⁩Float: ⁦0⁩dFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦23⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦7⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦5⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Supply” needs a pace ⁦30.3⁩× faster than it has kept

It earned ⁦10%⁩ in 408 days; the forecast assumes the rest in 121 days. At the pace so far it finishes on ⁦2036-11-16⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 224 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

122
216
355
273
153
G1G2G3G4G5

The critical chain

In date order, to final acceptance

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close