Jeddah Administrative Courts Complex
Remove from watchlistA new complex for the Jeddah administrative and appeal courts, with 40 courtrooms and offices for the judicial circuits.
Budget (BAC)
Actual cost
44% of budget
Progress
Planned 50%
Estimate at completion
SAR +35.3M
SPI · CPI
Forecast finish
95 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control19 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate15 March 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate18 October 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate15 November 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate30 January 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate19 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth