Jeddah Administrative Courts Complex
Remove from watchlistA new complex for the Jeddah administrative and appeal courts, with 40 courtrooms and offices for the judicial circuits.
Budget (BAC)
Actual cost
44% of budget
Progress
Planned 50%
Estimate at completion
SAR +35.3M
SPI · CPI
Forecast finish
95 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control19 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate15 March 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate18 October 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate15 November 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate30 January 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate19 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+91 days vs approved
- Critical activities
- 8
- of 10 open activities
- Late activities
- 7
- past their baseline finish
- Schedule performance
- 0.42
- earned ÷ planned value
- Next milestone
- in 75 days
- Build complete
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
23 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 10 open activities, data date 2026-10-28
“Structure” needs a pace 5.2× faster than it has kept
It earned 66% in 414 days; the forecast assumes the rest in 41 days. At the pace so far it finishes on 2027-05-29.
Milestones slip 235 days on average
Each milestone’s slip in days, in date order; the later ones slip more than the early ones.
The critical chain
In date order, to final acceptance