Board Backup Data Centre
Add to watchlistA Tier III backup data centre that keeps Mueen and the judicial systems running and recovers them after a disaster.
Budget (BAC)
Actual cost
79% of budget
Progress
Planned 80%
Estimate at completion
SAR +14.6M
SPI · CPI
Forecast finish
38 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control7 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionConditional goDate18 October 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate6 May 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate24 May 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate11 July 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate7 September 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+40 days vs approved
- Critical activities
- 5
- of 6 open activities
- Late activities
- 4
- past their baseline finish
- Schedule performance
- 0.73
- earned ÷ planned value
- Next milestone
- in 41 days
- Testing & acceptance complete
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
22 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 6 open activities, data date 2026-10-28
“System testing” needs a pace 3.5× faster than it has kept
It earned 70% in 206 days; the forecast assumes the rest in 25 days. At the pace so far it finishes on 2027-01-24.
Milestones slip 98 days on average — and it is getting worse
Each milestone’s slip in days, in date order; the later ones slip more than the early ones.
The critical chain
In date order, to final acceptance