Judges & Judicial Staff Academy
Add to watchlistDevelopment tracks for new judges, clerks and leaders with accredited academic partners.
Budget (BAC)
Actual cost
4% of budget
Progress
Planned 4%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
PlanningPhase 4 of 11
Next gate:Approval10 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate27 February 2026Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 August 2026Planning · Current phasePlanning · Current phase
- Gate into «Approval»DecisionNot held yetDate10 September 2026Approval · Not startedApproval · Not started
- Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
- Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Closure readiness
Closure planned after the forecast finish on 2027-12-31
A preview of what closure will need, with the planned dates, and the lessons captured so far.
Closure checklist
Seven mandatory items before any project closes.
- 1
Deliverables acceptedNot started
Final acceptance of every deliverable
Abdulmajeed R. Al-DosariPlanned 2027-12-21
- 2
Financial closureNot started
Spend reconciled, commitments closed
Khalid N. Al-MutairiPlanned 2028-01-20
- 3
Contract closureNot started
Contracts closed, retention released
Khalid N. Al-MutairiPlanned 2028-01-30
- 4
Documents archivedNot started
Documents archived with classification
Ghada A. Al-ShahraniPlanned 2028-01-25
- 5
Lessons learnedNot started
Lessons-learned session
Ghada A. Al-ShahraniPlanned 2028-01-15
- 6
Benefits owner assignedNot started
Benefits handed to their owner with a measurement plan
Abdulmajeed R. Al-DosariPlanned 2028-01-10
- 7
Final report approvedNot started
Final report and its approval
Ghada A. Al-ShahraniPlanned 2028-02-04
Post-implementation review
Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?
The review comes after closure
About three months after the forecast finish (2027-12-31), with the sponsor and the benefits owner.
Lessons learned
0 lessons — offered automatically to similar projects when they are created.
No lessons captured yet
Capture what the team learned during delivery; closure needs at least one.
Benefits handover
Each benefit moves from the project manager to an owner who measures it after closure.
No benefits recorded for this project.