PRJ-2026-029On track4PlanningWaterfall

Judges & Judicial Staff Academy

Add to watchlist

Development tracks for new judges, clerks and leaders with accredited academic partners.

Budget (BAC)

SAR 7.5M

Actual cost

SAR 300K

⁦4%⁩ of budget

Progress

⁦4%⁩

Planned ⁦4%⁩

Estimate at completion

SAR 7.5M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

PlanningPhase ⁦4⁩ of ⁦11⁩

Next gate:Approval10 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate27 February 2026Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate16 August 2026Planning · Current phasePlanning · Current phase
  5. Gate into «Approval»DecisionNot held yetDate10 September 2026Approval · Not startedApproval · Not started
  6. Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 7.5M split into spent, committed and left, with the estimate at completion

EAC SAR 7.5M
Revised request SAR 7.5M
  • Actual spendSAR 300K
  • Committed, not spentSAR 600K
  • Allotted, uncommittedSAR 6.4M
  • Contingency availableSAR 225K

Budget

Original budgetwhen the first baseline was approved
SAR 7.5M
Approved budgetafter approved change requests
SAR 7.5M
Current budgetavailable to spend now
SAR 7.5M
Revised budgetif the pending changes are approved
SAR 7.5M

Commitments

Commitmentssigned contracts and purchase orders
SAR 900K
Contracts0 active contracts
SAR 0
Purchase orders⁦0⁩ orders
SAR 900K
Remaining budgetapproved less actual
SAR 7.2M

Spend & outlook

Actual costincluding accruals
SAR 300K
Accrualswork done, not yet invoiced
SAR 12K
Estimate at completionthe PM’s bottom-up forecast
SAR 7.5M
ContingencySAR 150K drawn of SAR 375K
SAR 225K

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 150K drawn of SAR 375K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 150K

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.580.320.300.59⁦−0.00⁩
2Analysis & design1.240.110.001.26⁦−0.02⁩
3Build2.910.250.002.96⁦−0.05⁩
4Testing & acceptance1.460.130.001.48⁦−0.02⁩
5Launch & handover1.090.090.001.11⁦−0.02⁩
Unallocated contingency0.230.000.000.11⁦+0.11⁩
Total7.500.900.307.50⁦+0.00⁩

Budget split

WBS

SAR 7.5M

Budget

  • Management & governanceSAR 582K⁦8%⁩
  • Analysis & designSAR 1.2M⁦16%⁩
  • BuildSAR 2.9M⁦39%⁩
  • Testing & acceptanceSAR 1.5M⁦19%⁩
  • Launch & handoverSAR 1.1M⁦15%⁩
  • Unallocated contingencySAR 225K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2028-08-23⁩+236

SPI(t) ⁦0.68⁩ against the approved finish ⁦2027-12-31⁩

Planned valuePV
SAR 618K
The value of the work that should be done by today.
PV
Earned valueEV
SAR 300K
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 300K
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 7.5M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−0.32⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.49
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 7.5M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 7.2M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 7.5M
  • If the rest goes to planSAR 7.5M
  • At cost and schedule performanceSAR 15.1M
  • The PM’s bottom-up estimateSAR 7.5M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 7.5M

Variance at completion: ⁦+0.00⁩ SAR M