PRJ-2026-028On track7ExecutionWaterfall

Execution Plan for the BOG 2030 Strategy

Add to watchlist

Turning the Board of Grievances 2030 strategy into portfolios, initiatives and KPIs, aligned with Saudi Vision 2030.

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦70%⁩ of budget

Progress

⁦70%⁩

Planned ⁦68%⁩

Estimate at completion

SAR 3.2M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control13 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate14 November 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate14 May 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate21 May 2026Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate13 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦0⁩ days vs approved

Original baseline⁦2026-12-15⁩
Approved baseline⁦2026-12-15⁩
Current forecast⁦2026-12-15⁩
By earned schedule⁦2027-01-24⁩
Critical activities
1
of ⁦6⁩ open activities
Late activities
3
past their baseline finish
Schedule performance
0.83
earned ÷ planned value
Next milestone
in 25 days
Testing & acceptance complete
Expand allCollapse all
Activity
Execution Plan for the BOG 2030 StrategyPlanned: ⁦2026-05-03⁩ → ⁦2026-12-15⁩Forecast: ⁦2026-05-03⁩ → ⁦2026-12-15⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2026-05-03⁩ → ⁦2026-06-27⁩Actual: ⁦2026-05-03⁩ → ⁦2026-07-12⁩
Project plan & baselinePlanned: ⁦2026-05-03⁩ → ⁦2026-06-06⁩Actual: ⁦2026-05-03⁩ → ⁦2026-06-15⁩
Monitoring & reportingPlanned: ⁦2026-05-24⁩ → ⁦2026-06-27⁩Actual: ⁦2026-05-30⁩ → ⁦2026-07-12⁩
Project plan approvedPlanned: ⁦2026-06-27⁩ → ⁦2026-06-27⁩Actual: ⁦2026-07-12⁩ → ⁦2026-07-12⁩Project plan approved
DiagnosisPlanned: ⁦2026-06-15⁩ → ⁦2026-08-09⁩Actual: ⁦2026-06-26⁩ → ⁦2026-09-04⁩
Current-state assessmentPlanned: ⁦2026-06-15⁩ → ⁦2026-07-19⁩Actual: ⁦2026-06-26⁩ → ⁦2026-08-08⁩
BenchmarkingPlanned: ⁦2026-07-06⁩ → ⁦2026-08-09⁩Actual: ⁦2026-07-23⁩ → ⁦2026-09-04⁩
Designs approvedPlanned: ⁦2026-08-09⁩ → ⁦2026-08-09⁩Actual: ⁦2026-09-04⁩ → ⁦2026-09-04⁩Designs approved
DesignPlanned: ⁦2026-07-27⁩ → ⁦2026-09-21⁩Actual: ⁦2026-08-19⁩ → ⁦2026-10-26⁩
Target modelPlanned: ⁦2026-07-27⁩ → ⁦2026-08-30⁩Actual: ⁦2026-08-19⁩ → ⁦2026-10-01⁩
RoadmapPlanned: ⁦2026-08-18⁩ → ⁦2026-09-21⁩Actual: ⁦2026-09-15⁩ → ⁦2026-10-26⁩
Build completePlanned: ⁦2026-09-21⁩ → ⁦2026-09-21⁩Actual: ⁦2026-10-26⁩ → ⁦2026-10-26⁩Build complete
ImplementationPlanned: ⁦2026-09-08⁩ → ⁦2026-11-02⁩Forecast: ⁦2026-09-08⁩ → ⁦2026-11-22⁩Float: ⁦1⁩d
Wave 1Planned: ⁦2026-09-08⁩ → ⁦2026-10-12⁩Forecast: ⁦2026-09-08⁩ → ⁦2026-11-11⁩Float: ⁦1⁩d+30
Wave 2Planned: ⁦2026-09-29⁩ → ⁦2026-11-02⁩Forecast: ⁦2026-11-04⁩ → ⁦2026-11-22⁩Float: ⁦1⁩d+20
Testing & acceptance completePlanned: ⁦2026-11-02⁩ → ⁦2026-11-02⁩Forecast: ⁦2026-11-22⁩ → ⁦2026-11-22⁩Float: ⁦23⁩dTesting & acceptance complete
Handover & knowledge transferPlanned: ⁦2026-10-21⁩ → ⁦2026-12-15⁩Forecast: ⁦2026-11-15⁩ → ⁦2026-12-15⁩Float: ⁦0⁩d
Knowledge transferPlanned: ⁦2026-10-21⁩ → ⁦2026-11-24⁩Forecast: ⁦2026-11-15⁩ → ⁦2026-12-03⁩Float: ⁦1⁩d+9
Final reportPlanned: ⁦2026-11-11⁩ → ⁦2026-12-15⁩Forecast: ⁦2026-11-26⁩ → ⁦2026-12-14⁩Float: ⁦1⁩d
Final handoverPlanned: ⁦2026-12-15⁩ → ⁦2026-12-15⁩Forecast: ⁦2026-12-15⁩ → ⁦2026-12-15⁩Float: ⁦0⁩dFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦21⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦6⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦0⁩ activities with no float

Every day lost on this chain is a day lost at launch. ⁦4⁩ more activities have three weeks of float or less.
Slippage pattern⁦84%⁩ confidence

Milestones slip 19 days on average

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

15
26
35
20
0
G1G2G3G4G5

The critical chain

In date order, to final acceptance