Execution Plan for the BOG 2030 Strategy
Add to watchlistTurning the Board of Grievances 2030 strategy into portfolios, initiatives and KPIs, aligned with Saudi Vision 2030.
Budget (BAC)
Actual cost
70% of budget
Progress
Planned 68%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control13 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate14 November 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate14 May 2026Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate21 May 2026Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate8 June 2026Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate13 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
0 days vs approved
- Critical activities
- 1
- of 6 open activities
- Late activities
- 3
- past their baseline finish
- Schedule performance
- 0.83
- earned ÷ planned value
- Next milestone
- in 25 days
- Testing & acceptance complete
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
21 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 6 open activities, data date 2026-10-28
Milestones slip 19 days on average
Each milestone’s slip in days, in date order; the later ones slip more than the early ones.
The critical chain
In date order, to final acceptance
Near-critical