PRJ-2026-025On track7ExecutionConstruction

Al-Jouf Administrative Court Rehabilitation

Add to watchlist

Rehabilitating the Al-Jouf administrative court building — courtrooms, MEP systems and accessible entrances.

Budget (BAC)

SAR 42M

Actual cost

SAR 14.8M

⁦35%⁩ of budget

Progress

⁦36%⁩

Planned ⁦35%⁩

Estimate at completion

SAR 41.2M

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control21 June 2027

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate25 April 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate17 November 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate8 December 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate21 June 2027Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 42M split into spent, committed and left, with the estimate at completion

EAC SAR 41.2M
Revised request SAR 42M
  • Actual spendSAR 14.8M
  • Committed, not spentSAR 21.2M
  • Allotted, uncommittedSAR 4.7M
  • Contingency availableSAR 1.3M

Budget

Original budgetwhen the first baseline was approved
SAR 42M
Approved budgetafter approved change requests
SAR 42M
Current budgetavailable to spend now
SAR 42M
Revised budgetif the pending changes are approved
SAR 42M

Commitments

Commitmentssigned contracts and purchase orders
SAR 36M
Contracts1 active contract
SAR 33M
Purchase orders⁦0⁩ orders
SAR 3M
Remaining budgetapproved less actual
SAR 27.2M

Spend & outlook

Actual costincluding accruals
SAR 14.8M
Accrualswork done, not yet invoiced
SAR 593K
Estimate at completionthe PM’s bottom-up forecast
SAR 41.2M
ContingencySAR 840K drawn of SAR 2.1M
SAR 1.3M

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 840K drawn of SAR 2.1M

  • Covering realised delivery risks⁦2026-08-29⁩SAR 840K

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance2.442.472.472.47⁦−0.03⁩
2Design & permits4.894.944.944.94⁦−0.05⁩
3Civil works15.4813.987.4115.40⁦+0.09⁩
4MEP works12.229.960.0012.09⁦+0.13⁩
5Handover5.704.650.005.64⁦+0.06⁩
Unallocated contingency1.260.000.000.63⁦+0.63⁩
Total42.0036.0014.8241.18⁦+0.82⁩

Budget split

WBS

SAR 42M

Budget

  • Management & governanceSAR 2.4M⁦6%⁩
  • Design & permitsSAR 4.9M⁦12%⁩
  • Civil worksSAR 15.5M⁦37%⁩
  • MEP worksSAR 12.2M⁦29%⁩
  • HandoverSAR 5.7M⁦14%⁩
  • Unallocated contingencySAR 1.3M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2028-05-28⁩+241

SPI(t) ⁦0.75⁩ against the approved finish ⁦2027-09-30⁩

Planned valuePV
SAR 23.6M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 15.1M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 14.8M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 42M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.30⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−8.50⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.02
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.64
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 41.2M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 26.4M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.82⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.99
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 41.2M
  • If the rest goes to planSAR 41.7M
  • At cost and schedule performanceSAR 56M
  • The PM’s bottom-up estimateSAR 41.2M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 41.2M

Variance at completion: ⁦+0.82⁩ SAR M