Original
Original baseline
- Finish
- 2027-09-30
- Budget
- SAR 42M
- 17 activities
Approved with the project plan at the planning gate.
Approved 2025-10-12 · by Eng. Turki A. Al-Anazi
Rehabilitating the Al-Jouf administrative court building — courtrooms, MEP systems and accessible entrances.
Budget (BAC)
Actual cost
35% of budget
Progress
Planned 35%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control21 June 2027
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-10-12 · by Eng. Turki A. Al-Anazi
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Mishari K. Al-Otaibi
What changed from version A to version B
Finish
2027-09-302027-10-04
+4 days
Budget
SAR 42MSAR 42M
0.00 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference