PRJ-2026-025On track7ExecutionConstruction

Al-Jouf Administrative Court Rehabilitation

Add to watchlist

Rehabilitating the Al-Jouf administrative court building — courtrooms, MEP systems and accessible entrances.

Budget (BAC)

SAR 42M

Actual cost

SAR 14.8M

⁦35%⁩ of budget

Progress

⁦36%⁩

Planned ⁦35%⁩

Estimate at completion

SAR 41.2M

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control21 June 2027

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate25 April 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate17 November 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate8 December 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate21 June 2027Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

2Achieved
1On track
2At risk
0Late
Average delay31 days
Apr 26Jul 26Oct 26Jan 27Apr 27Jul 27Oct 27
Contractual
Build completePlanned: ⁦2026-12-19⁩Forecast / actual: ⁦2027-02-06⁩Delay: 49 daysG3 +49
Executive
Project plan approvedPlanned: ⁦2026-03-09⁩Forecast / actual: ⁦2026-04-07⁩Delay: 29 daysG1 +29
Payment
Final handoverPlanned: ⁦2027-09-30⁩Forecast / actual: ⁦2027-10-04⁩Delay: 4 daysG5 +4
Regulatory
Testing & acceptance completePlanned: ⁦2027-06-08⁩Forecast / actual: ⁦2027-06-30⁩Delay: 22 daysG4 +22
Project
Designs approvedPlanned: ⁦2026-07-01⁩Forecast / actual: ⁦2026-08-21⁩Delay: 51 daysG2 +51

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-03-09⁩⁦2026-04-07⁩⁦+29⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saAchieved1Approved
Designs approvedMS-G2Project⁦2026-07-01⁩⁦2026-08-21⁩⁦+51⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-12-19⁩⁦2027-02-06⁩⁦+49⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saAt risk0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2027-06-08⁩⁦2027-06-30⁩⁦+22⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saAt risk0Not requested
Final handoverMS-G5Payment⁦2027-09-30⁩⁦2027-10-04⁩⁦+4⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline025-D1ApprovedEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-01-11⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Monitoring & reporting025-D2ApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-03-09⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Detailed design025-D3ApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-05-05⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Permits & approvals025-D4ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-07-01⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Site works & excavation025-D5ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-08-27⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Structure025-D6Under reviewEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-10-23⁩V1⁦1⁩ of ⁦2⁩