Al-Jouf Administrative Court Rehabilitation
Add to watchlistRehabilitating the Al-Jouf administrative court building — courtrooms, MEP systems and accessible entrances.
Budget (BAC)
Actual cost
35% of budget
Progress
Planned 35%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control21 June 2027
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate25 April 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate17 November 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate8 December 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate4 February 2026Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate21 June 2027Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-03-09 | 2026-04-07 | +29 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-07-01 | 2026-08-21 | +51 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-12-19 | 2027-02-06 | +49 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa | At risk | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-06-08 | 2027-06-30 | +22 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-09-30 | 2027-10-04 | +4 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline025-D1 | Approved | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2026-01-11 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting025-D2 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2026-03-09 | V1 | 2 of 2 |
| Deliverable: Detailed design025-D3 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2026-05-05 | V1 | 2 of 2 |
| Deliverable: Permits & approvals025-D4 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2026-07-01 | V1 | 2 of 2 |
| Deliverable: Site works & excavation025-D5 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2026-08-27 | V1 | 2 of 2 |
| Deliverable: Structure025-D6 | Under review | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2026-10-23 | V1 | 1 of 2 |