PRJ-2026-025On track7ExecutionConstruction
Al-Jouf Administrative Court Rehabilitation
Add to watchlistRehabilitating the Al-Jouf administrative court building — courtrooms, MEP systems and accessible entrances.
Project managerEng. Mishari K. Al-OtaibiSponsorEng. Turki A. Al-AnaziProgrammeFacilities Rehabilitation & Efficiency Programme
Budget (BAC)
SAR 42M
Actual cost
SAR 14.8M
35% of budget
Progress
36%
Planned 35%
Estimate at completion
SAR 41.2M
SPI · CPI
1.03Schedule performance index · 1.031.02Cost performance index · 1.02
Forecast finish
2027-09-30
On baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control21 June 2027
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate25 April 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate17 November 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate8 December 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate4 February 2026Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate21 June 2027Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth
Allotted to work40.7M17 elements
Unallocated contingency1.3MSAR 2.1M
Budget at completion42MPRJ-2026-025
Weighted progress36%Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Total36%40.7414.82