Al-Jouf Administrative Court Rehabilitation
Add to watchlistRehabilitating the Al-Jouf administrative court building — courtrooms, MEP systems and accessible entrances.
Budget (BAC)
Actual cost
35% of budget
Progress
Planned 35%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control21 June 2027
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate25 April 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate17 November 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate8 December 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate4 February 2026Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate21 June 2027Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+4 days vs approved
- Critical activities
- 8
- of 10 open activities
- Late activities
- 7
- past their baseline finish
- Schedule performance
- 0.64
- earned ÷ planned value
- Next milestone
- in 101 days
- Build complete
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
23 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 10 open activities, data date 2026-10-28
“Structure” needs a pace 2.5× faster than it has kept
It earned 42% in 96 days; the forecast assumes the rest in 53 days. At the pace so far it finishes on 2027-03-10.
Milestones slip 43 days on average — and it is getting worse
Each milestone’s slip in days, in date order; the later ones slip more than the early ones.
The critical chain
In date order, to final acceptance