Judicial Data Governance & Master Data
Add to watchlistApply NDMO policies and build one master register of cases and parties.
Budget (BAC)
Actual cost
65% of budget
Progress
Planned 70%
Estimate at completion
SAR +1.1M
SPI · CPI
Forecast finish
18 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control20 October 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate14 February 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate29 August 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate13 September 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate24 October 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate20 October 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+16 days vs approved
- Critical activities
- 6
- of 8 open activities
- Late activities
- 5
- past their baseline finish
- Schedule performance
- 0.64
- earned ÷ planned value
- Next milestone
- in 16 days
- Build complete
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
22 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 8 open activities, data date 2026-10-28
“Integrations” needs a pace 3.5× faster than it has kept
It earned 77% in 185 days; the forecast assumes the rest in 16 days. At the pace so far it finishes on 2026-12-22.
Milestones slip 78 days on average
Each milestone’s slip in days, in date order; the later ones slip more than the early ones.
The critical chain
In date order, to final acceptance