Judicial Indicators Dashboard & Performance Measurement
Add to watchlistJudicial and institutional KPIs — time to judgment, appeal outcomes, video hearings — wired to automated scorecards down to circuit level.
Budget (BAC)
Actual cost
76% of budget
Progress
Planned 75%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control25 October 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate21 March 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate1 October 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate15 October 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate23 November 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate25 October 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Closure readiness
Closure planned after the forecast finish on 2026-12-24
A preview of what closure will need, with the planned dates, and the lessons captured so far.
Closure checklist
Seven mandatory items before any project closes.
- 1
Deliverables acceptedNot started
Final acceptance of every deliverable
Dr. Amal F. Al-SudairiPlanned 2026-12-14
- 2
Financial closureNot started
Spend reconciled, commitments closed
Khalid N. Al-MutairiPlanned 2027-01-13
- 3
Contract closureNot started
Contracts closed, retention released
Khalid N. Al-MutairiPlanned 2027-01-23
- 4
Documents archivedNot started
Documents archived with classification
Tariq S. Al-YamiPlanned 2027-01-18
- 5
Lessons learnedNot started
Lessons-learned session
Tariq S. Al-YamiPlanned 2027-01-08
- 6
Benefits owner assignedNot started
Benefits handed to their owner with a measurement plan
Dr. Amal F. Al-SudairiPlanned 2027-01-03
- 7
Final report approvedNot started
Final report and its approval
Tariq S. Al-YamiPlanned 2027-01-28
Post-implementation review
Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?
The review comes after closure
About three months after the forecast finish (2026-12-24), with the sponsor and the benefits owner.
Lessons learned
0 lessons — offered automatically to similar projects when they are created.
No lessons captured yet
Capture what the team learned during delivery; closure needs at least one.
Benefits handover
Each benefit moves from the project manager to an owner who measures it after closure.
No benefits recorded for this project.