Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-012On track7ExecutionAgile

Judicial Indicators Dashboard & Performance Measurement

Add to watchlist

Judicial and institutional KPIs — time to judgment, appeal outcomes, video hearings — wired to automated scorecards down to circuit level.

Budget (BAC)

SAR 9.8M

Actual cost

SAR 7.4M

⁦76%⁩ of budget

Progress

⁦76%⁩

Planned ⁦75%⁩

Estimate at completion

SAR 9.8M

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control25 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate21 March 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate1 October 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate15 October 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate23 November 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate25 October 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Board of Grievances

Project charter

Judicial Indicators Dashboard & Performance Measurement

APPROVEDV2Approved ⁦2025-09-05⁩

1Project identity

Project name
Judicial Indicators Dashboard & Performance Measurement
Project code
PRJ-2026-012
Sponsor
Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieDirector General, Decision Support CentreP-009m.alsubaie@bog.gov.sa
Project manager
Tariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.sa
Business owner
Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategic Planning & PerformanceP-015a.alsudairi@bog.gov.sa
Portfolio & programme
Institutional Excellence & Governance PortfolioInstitutional Excellence & Talent Programme
Type & methodology
Transformation · Agile
Current phase
7Execution

2Background & rationale

Judicial and institutional KPIs — time to judgment, appeal outcomes, video hearings — wired to automated scorecards down to circuit level.

3Objectives

  1. 1Develop the organisational and information environment

4Scope

In scope

  • Judicial and institutional KPIs — time to judgment, appeal outcomes, video hearings — wired to automated scorecards down to circuit level.
  • As-is and to-be analysis
  • Change management plan

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

  1. 1As-is and to-be analysis
  2. 2Change management plan
  3. 3Adoption measures

6Deliverables

1Project management plan⁦2025-09-26⁩
2Main deliverable — stage 1⁦2026-05-10⁩
3Main deliverable — final stage⁦2026-10-25⁩
4Final report⁦2026-12-31⁩

7Key milestones

  1. Charter approved⁦2025-09-05⁩
  2. Contract signed⁦2025-11-23⁩
  3. 50% of works complete⁦2026-05-10⁩
  4. Provisional acceptance⁦2026-11-23⁩
  5. Closure⁦2026-12-31⁩

8Budget

  • Main contract⁦72.4%⁩7.1M
  • Supervision & consulting⁦13.3%⁩1.3M
  • Internal team⁦9.2%⁩900K
  • Contingency reserve (⁦5%⁩)⁦5.1%⁩500K
The owning sector’s approved budgetTotal9.8M

9Timeline

Start
2025-09-0715 Rabiʻ I 1447 AH
Baseline finish
2026-12-3122 Rajab 1448 AH
Duration
⁦16⁩ months

10Key risks

  • No risks recorded yet.

11Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

  • Named internal staff available throughout
  • Approvals land within workflow SLAs

13Stakeholders

  • Project sponsorDecisions and funding
  • Business ownerAccepts deliverables, owns benefits
  • Projects Follow-up Office (EPMO)Governance and compliance

14Success criteria

  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • EPMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, issues, weekly statusWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close