Budget (BAC)
Actual cost
76% of budget
Progress
Planned 75%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control25 October 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate21 March 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate1 October 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate15 October 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate23 November 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate25 October 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-01-03 | 2026-01-27 | +24 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-04-03 | 2026-05-17 | +44 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-07-03 | 2026-09-03 | +62 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-10-01 | 2027-01-03 | +94 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-31 | 2027-01-23 | +23 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline012-D1 | Approved | Tariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.sa | Dr. Amal F. Al-Sudairi | 2025-11-18 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting012-D2 | Approved | Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategic Planning & PerformanceP-015a.alsudairi@bog.gov.sa | Dr. Amal F. Al-Sudairi | 2026-01-03 | V1 | 2 of 2 |
| Deliverable: Current-state assessment012-D3 | Approved | Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategic Planning & PerformanceP-015a.alsudairi@bog.gov.sa | Dr. Amal F. Al-Sudairi | 2026-02-17 | V1 | 2 of 2 |
| Deliverable: Benchmarking012-D4 | Approved | Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieDirector General, Decision Support CentreP-009m.alsubaie@bog.gov.sa | Dr. Amal F. Al-Sudairi | 2026-04-03 | V1 | 2 of 2 |
| Deliverable: Target model012-D5 | Approved | Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieDirector General, Decision Support CentreP-009m.alsubaie@bog.gov.sa | Dr. Amal F. Al-Sudairi | 2026-05-19 | V1 | 2 of 2 |
| Deliverable: Roadmap012-D6 | Approved | Tariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.sa | Dr. Amal F. Al-Sudairi | 2026-07-03 | V1 | 2 of 2 |