PRJ-2026-012On track7ExecutionAgile

Judicial Indicators Dashboard & Performance Measurement

Add to watchlist

Judicial and institutional KPIs — time to judgment, appeal outcomes, video hearings — wired to automated scorecards down to circuit level.

Budget (BAC)

SAR 9.8M

Actual cost

SAR 7.4M

⁦76%⁩ of budget

Progress

⁦76%⁩

Planned ⁦75%⁩

Estimate at completion

SAR 9.8M

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control25 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate21 March 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate1 October 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate15 October 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate23 November 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate25 October 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

3Achieved
0On track
1At risk
1Late
Average delay49 days
Jan 26Apr 26Jul 26Oct 26Jan 27
Contractual
Build completePlanned: ⁦2026-07-03⁩Forecast / actual: ⁦2026-09-03⁩Delay: 62 daysG3 +62
Executive
Project plan approvedPlanned: ⁦2026-01-03⁩Forecast / actual: ⁦2026-01-27⁩Delay: 24 daysG1 +24
Payment
Final handoverPlanned: ⁦2026-12-31⁩Forecast / actual: ⁦2027-01-23⁩Delay: 23 daysG5 +23
Regulatory
Testing & acceptance completePlanned: ⁦2026-10-01⁩Forecast / actual: ⁦2027-01-03⁩Delay: 94 daysG4 +94
Project
Designs approvedPlanned: ⁦2026-04-03⁩Forecast / actual: ⁦2026-05-17⁩Delay: 44 daysG2 +44

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-01-03⁩⁦2026-01-27⁩⁦+24⁩ daysTariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.saAchieved1Approved
Designs approvedMS-G2Project⁦2026-04-03⁩⁦2026-05-17⁩⁦+44⁩ daysTariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-07-03⁩⁦2026-09-03⁩⁦+62⁩ daysTariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.saAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-10-01⁩⁦2027-01-03⁩⁦+94⁩ daysTariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.saLate0Not requested
Final handoverMS-G5Payment⁦2026-12-31⁩⁦2027-01-23⁩⁦+23⁩ daysTariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.saAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline012-D1ApprovedTariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.saDr. Amal F. Al-Sudairi⁦2025-11-18⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Monitoring & reporting012-D2ApprovedDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategic Planning & PerformanceP-015a.alsudairi@bog.gov.saDr. Amal F. Al-Sudairi⁦2026-01-03⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Current-state assessment012-D3ApprovedDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategic Planning & PerformanceP-015a.alsudairi@bog.gov.saDr. Amal F. Al-Sudairi⁦2026-02-17⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Benchmarking012-D4ApprovedDr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieDirector General, Decision Support CentreP-009m.alsubaie@bog.gov.saDr. Amal F. Al-Sudairi⁦2026-04-03⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Target model012-D5ApprovedDr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieDirector General, Decision Support CentreP-009m.alsubaie@bog.gov.saDr. Amal F. Al-Sudairi⁦2026-05-19⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Roadmap012-D6ApprovedTariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeP-040t.alyami@bog.gov.saDr. Amal F. Al-Sudairi⁦2026-07-03⁩V1⁦2⁩ of ⁦2⁩