Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-008On track8Monitoring & ControlScrum

Khabeer Platform — Release 2

Add to watchlist

A platform to register accredited experts, assign them to cases and follow their reports online until they are filed in the case record.

Budget (BAC)

SAR 18.4M

Actual cost

SAR 16.4M

⁦89%⁩ of budget

Progress

⁦91%⁩

Planned ⁦90%⁩

Estimate at completion

SAR 18M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

Monitoring & ControlPhase ⁦8⁩ of ⁦11⁩

Next gate:Handover15 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate15 November 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate2 June 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate19 June 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate4 August 2025Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate11 September 2026Monitoring & Control · Current phaseMonitoring & Control · Current phase
  9. Gate into «Handover»DecisionNot held yetDate15 October 2026Handover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦0⁩ days vs approved

Original baseline⁦2026-11-30⁩
Approved baseline⁦2026-11-30⁩
Current forecast⁦2026-11-30⁩
By earned schedule⁦2027-03-02⁩
Critical activities
1
of ⁦3⁩ open activities
Late activities
1
past their baseline finish
Schedule performance
0.92
earned ÷ planned value
Next milestone
in 33 days
Final handover
Expand allCollapse all
Activity
Khabeer Platform — Release 2Planned: ⁦2025-05-04⁩ → ⁦2026-11-30⁩Forecast: ⁦2025-05-04⁩ → ⁦2026-11-30⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-05-04⁩ → ⁦2025-09-10⁩Actual: ⁦2025-05-04⁩ → ⁦2025-09-28⁩
Project plan & baselinePlanned: ⁦2025-05-04⁩ → ⁦2025-07-22⁩Actual: ⁦2025-05-04⁩ → ⁦2025-08-02⁩
Monitoring & reportingPlanned: ⁦2025-06-23⁩ → ⁦2025-09-10⁩Actual: ⁦2025-06-29⁩ → ⁦2025-09-28⁩
Project plan approvedPlanned: ⁦2025-09-10⁩ → ⁦2025-09-10⁩Actual: ⁦2025-09-28⁩ → ⁦2025-09-28⁩Project plan approved
Analysis & designPlanned: ⁦2025-08-11⁩ → ⁦2025-12-18⁩Actual: ⁦2025-08-25⁩ → ⁦2026-01-19⁩
Business requirementsPlanned: ⁦2025-08-11⁩ → ⁦2025-10-29⁩Actual: ⁦2025-08-25⁩ → ⁦2025-11-23⁩
Solution designPlanned: ⁦2025-09-30⁩ → ⁦2025-12-18⁩Actual: ⁦2025-10-20⁩ → ⁦2026-01-19⁩
Designs approvedPlanned: ⁦2025-12-18⁩ → ⁦2025-12-18⁩Actual: ⁦2026-01-19⁩ → ⁦2026-01-19⁩Designs approved
BuildPlanned: ⁦2025-11-18⁩ → ⁦2026-05-16⁩Actual: ⁦2025-12-16⁩ → ⁦2026-07-07⁩
Release 1Planned: ⁦2025-11-18⁩ → ⁦2026-02-06⁩Actual: ⁦2025-12-16⁩ → ⁦2026-03-16⁩
Release 2Planned: ⁦2026-01-07⁩ → ⁦2026-03-27⁩Actual: ⁦2026-02-10⁩ → ⁦2026-05-12⁩
IntegrationsPlanned: ⁦2026-02-25⁩ → ⁦2026-05-16⁩Actual: ⁦2026-04-08⁩ → ⁦2026-07-07⁩
Build completePlanned: ⁦2026-05-16⁩ → ⁦2026-05-16⁩Actual: ⁦2026-07-07⁩ → ⁦2026-07-07⁩Build complete
Testing & acceptancePlanned: ⁦2026-04-16⁩ → ⁦2026-08-23⁩Actual: ⁦2026-06-03⁩ → ⁦2026-10-26⁩
System testingPlanned: ⁦2026-04-16⁩ → ⁦2026-07-04⁩Actual: ⁦2026-06-03⁩ → ⁦2026-09-01⁩
User acceptance testingPlanned: ⁦2026-06-05⁩ → ⁦2026-08-23⁩Actual: ⁦2026-07-30⁩ → ⁦2026-10-26⁩
Testing & acceptance completePlanned: ⁦2026-08-23⁩ → ⁦2026-08-23⁩Actual: ⁦2026-10-26⁩ → ⁦2026-10-26⁩Testing & acceptance complete
Launch & handoverPlanned: ⁦2026-07-24⁩ → ⁦2026-11-30⁩Forecast: ⁦2026-07-24⁩ → ⁦2026-11-30⁩Float: ⁦0⁩d
Training & changePlanned: ⁦2026-07-24⁩ → ⁦2026-10-11⁩Forecast: ⁦2026-07-24⁩ → ⁦2026-11-13⁩Float: ⁦4⁩d+33
Go-live & handoverPlanned: ⁦2026-09-12⁩ → ⁦2026-11-30⁩Forecast: ⁦2026-11-05⁩ → ⁦2026-11-26⁩Float: ⁦4⁩d
Final handoverPlanned: ⁦2026-11-30⁩ → ⁦2026-11-30⁩Forecast: ⁦2026-11-30⁩ → ⁦2026-11-30⁩Float: ⁦0⁩dFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦22⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦3⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦0⁩ activities with no float

Every day lost on this chain is a day lost at launch. ⁦2⁩ more activities have three weeks of float or less.
Slippage pattern⁦84%⁩ confidence

Milestones slip 33 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

18
32
52
64
0
G1G2G3G4G5

The critical chain

In date order, to final acceptance

Near-critical

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close