Khabeer Platform — Release 2
Add to watchlistA platform to register accredited experts, assign them to cases and follow their reports online until they are filed in the case record.
Budget (BAC)
Actual cost
89% of budget
Progress
Planned 90%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
Monitoring & ControlPhase 8 of 11
Next gate:Handover15 October 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate15 November 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate2 June 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate19 June 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate4 August 2025Execution · CompleteExecution · Complete
- Gate into «Monitoring & Control»DecisionGoDate11 September 2026Monitoring & Control · Current phaseMonitoring & Control · Current phase
- Gate into «Handover»DecisionNot held yetDate15 October 2026Handover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
0 days vs approved
- Critical activities
- 1
- of 3 open activities
- Late activities
- 1
- past their baseline finish
- Schedule performance
- 0.92
- earned ÷ planned value
- Next milestone
- in 33 days
- Final handover
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
22 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 3 open activities, data date 2026-10-28
Milestones slip 33 days on average — and it is getting worse
Each milestone’s slip in days, in date order; the later ones slip more than the early ones.
The critical chain
In date order, to final acceptance
Near-critical