Dammam Administrative Courts Complex — Rehabilitation & Extension
Remove from watchlistRebuilding the existing complex of the Eastern Province administrative and appeal courts and adding a new wing with 28 courtrooms.
Budget (BAC)
Actual cost
81% of budget
Progress
Planned 92%
Estimate at completion
SAR +78.5M
SPI · CPI
Forecast finish
126 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control14 May 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionConditional goDate28 July 2023Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate4 March 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate2 April 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate20 June 2024Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate14 May 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth