East Waha Wastewater Treatment Plant
Remove from watchlistA 120,000 m³/day tertiary treatment plant with a reuse network for irrigation.
Budget (BAC)
Actual cost
81% of budget
Progress
Planned 92%
Estimate at completion
SAR +78.5M
SPI · CPI
Forecast finish
126 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control14 May 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionConditional goDate28 July 2023Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate4 March 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate2 April 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate20 June 2024Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate14 May 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Project lifecycle and its gates
Current phase: Execution. Pick a gate on the track to review it.
- Gate into «Feasibility»DecisionConditional goDate28 July 2023Mandatory criteria met, with points to close during the next phase.IdeaComplete
- Gate into «Initiation»DecisionGoDate15 November 2023All criteria and required documents met.FeasibilityComplete
- Gate into «Planning»DecisionGoDate14 January 2024All criteria and required documents met.InitiationComplete
- Gate into «Approval»DecisionConditional goDate4 March 2024Mandatory criteria met, with points to close during the next phase.PlanningComplete
- Gate into «Procurement»DecisionGoDate2 April 2024All criteria and required documents met.ApprovalComplete
- Gate into «Execution»DecisionGoDate20 June 2024All criteria and required documents met.ProcurementComplete
- Gate into «Monitoring & Control»DecisionNot held yetDate14 May 2026ExecutionCurrent phaseCurrent phase
- Gate into «Handover»DecisionNot held yet8Monitoring & ControlNot started
- Gate into «Closure»DecisionNot held yet9HandoverNot started
- Gate into «Benefits Realization»DecisionNot held yet10ClosureNot started
- 11Benefits RealizationNot started
Operational readiness gate — into hypercare & monitoring
Gate readiness
Meets the pass mark
Automated control: no move until the criteria are met
- 1 mandatory checklist item open
- 2 required documents not approved
Checklist
5 of 7 done
- All in-scope services builtMandatory
- User acceptance testing passedMandatory
- Penetration test passed — no critical/high findingsMandatory
- Data migrated and reconciledMandatory
- Operations & support plan, SLAMandatory
- Staff trained
- Launch rollback plan
Required documents
2 of 4 approved
- UAT reportApproved · V1
- Penetration test reportNot submitted
- Operations & support planApproved · V1
- Data migration reconciliationSubmitted — awaiting acceptance · V1
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Deliverables completeweight 30%Met
Awaiting evidence from the project team.
Quality & securityweight 30%Met
Awaiting evidence from the project team.
Operations & support readinessweight 20%Met
Awaiting evidence from the project team.
User & change readinessweight 20%
Awaiting evidence from the project team.
Approvers
Projects Steering Committee
- Eng. Abdullah S. Al-QahtaniSteering Committee chairVote pending
- Eng. Turki A. Al-AnaziProject sponsorVote pending
- Dr. Noura M. Al-OtaibiPMO directorVote pending
- Eng. Bandar M. Al-ShammariBusiness ownerVote pending