PRJ-2026-004Critical7ExecutionConstruction

East Waha Wastewater Treatment Plant

Remove from watchlist

A 120,000 m³/day tertiary treatment plant with a reuse network for irrigation.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 412M

Actual cost

SAR 333.5M

⁦81%⁩ of budget

Progress

⁦68%⁩

Planned ⁦92%⁩

Estimate at completion

SAR 490.5M

SAR +78.5M

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control14 May 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate28 July 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate4 March 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate2 April 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate20 June 2024Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate14 May 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2026-09-30⁩
    Budget
    SAR 390.6M
    ⁦17⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2024-01-14⁩ · by Eng. Turki A. Al-Anazi

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-03-08⁩
    ⁦+159⁩ days
    Budget
    SAR 412M
    ⁦17⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Eng. Waleed O. Al-Juhani

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2026-09-30⁩⁦2027-03-08⁩

⁦+159⁩ days

Budget

SAR 390.6MSAR 412M

⁦+21.40⁩ SAR M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2025-012025-072026-012026-072027-01
  • Project plan approved⁦+104⁩
  • Designs approved⁦+183⁩
  • Build complete⁦+302⁩
  • Testing & acceptance complete⁦+296⁩
  • Final handover⁦+159⁩

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+5.45⁩
  • 2Design & permits⁦+10.90⁩
  • 3Civil works⁦+42.76⁩
  • 4MEP works⁦+17.63⁩
  • 5Handover⁦+16.16⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Eng. Waleed O. Al-Juhani
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2024-01-14⁩by Eng. Turki A. Al-Anazi