PRJ-2026-004Critical7ExecutionConstruction

East Waha Wastewater Treatment Plant

Remove from watchlist

A 120,000 m³/day tertiary treatment plant with a reuse network for irrigation.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 412M

Actual cost

SAR 333.5M

⁦81%⁩ of budget

Progress

⁦68%⁩

Planned ⁦92%⁩

Estimate at completion

SAR 490.5M

SAR +78.5M

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control14 May 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate28 July 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate4 March 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate2 April 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate20 June 2024Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate14 May 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

3Achieved
0On track
0At risk
2Late
Average delay209 days
Oct 24Jan 25Apr 25Jul 25Oct 25Jan 26Apr 26Jul 26Oct 26Jan 27Apr 27
Contractual
Build completePlanned: ⁦2025-09-02⁩Forecast / actual: ⁦2026-07-01⁩Delay: 302 daysG3 +302
Executive
Project plan approvedPlanned: ⁦2024-08-05⁩Forecast / actual: ⁦2024-11-17⁩Delay: 104 daysG1 +104
Payment
Final handoverPlanned: ⁦2026-09-30⁩Forecast / actual: ⁦2027-03-08⁩Delay: 159 daysG5 +159
Regulatory
Testing & acceptance completePlanned: ⁦2026-04-26⁩Forecast / actual: ⁦2027-02-16⁩Delay: 296 daysG4 +296
Project
Designs approvedPlanned: ⁦2025-01-09⁩Forecast / actual: ⁦2025-07-11⁩Delay: 183 daysG2 +183

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2024-08-05⁩⁦2024-11-17⁩⁦+104⁩ daysEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.saAchieved1Approved
Designs approvedMS-G2Project⁦2025-01-09⁩⁦2025-07-11⁩⁦+183⁩ daysEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.saAchieved1Approved
Build completeMS-G3Contractual⁦2025-09-02⁩⁦2026-07-01⁩⁦+302⁩ daysEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.saAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-04-26⁩⁦2027-02-16⁩⁦+296⁩ daysEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.saLate0Not requested
Final handoverMS-G5Payment⁦2026-09-30⁩⁦2027-03-08⁩⁦+159⁩ daysEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.saLate0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline004-D1ApprovedEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.saEng. Bandar M. Al-Shammari⁦2024-05-19⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Monitoring & reporting004-D2ApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDeputy, InfrastructureP-013b.alshammari@alwaha.gov.saEng. Bandar M. Al-Shammari⁦2024-08-05⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Detailed design004-D3ApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDeputy, InfrastructureP-013b.alshammari@alwaha.gov.saEng. Bandar M. Al-Shammari⁦2024-10-23⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Permits & approvals004-D4ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziVP, Projects & InfrastructureP-010t.alanazi@alwaha.gov.saEng. Bandar M. Al-Shammari⁦2025-01-09⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Site works & excavation004-D5ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziVP, Projects & InfrastructureP-010t.alanazi@alwaha.gov.saEng. Bandar M. Al-Shammari⁦2025-03-29⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Structure004-D6ApprovedEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.saEng. Bandar M. Al-Shammari⁦2025-06-16⁩V1⁦2⁩ of ⁦2⁩
⁦1⁩–⁦6⁩ of ⁦6⁩