10My actionsNotifications
PRJ-2026-004Critical7ExecutionConstruction

East Waha Wastewater Treatment Plant

Remove from watchlist

A 120,000 m³/day tertiary treatment plant with a reuse network for irrigation.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 412M

Actual cost

SAR 333.5M

⁦81%⁩ of budget

Progress

⁦68%⁩

Planned ⁦92%⁩

Estimate at completion

SAR 490.5M

SAR +78.5M

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control14 May 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate28 July 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate4 March 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate2 April 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate20 June 2024Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate14 May 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Team & roles

4 members, about ⁦2.1⁩ full-time equivalents

Leadership

2 members

  • Eng. Waleed O. Al-JuhaniProject manager⁦70%⁩Allocated ⁦130%⁩ across all projectsA
  • Eng. Turki A. Al-AnaziProject sponsor⁦20%⁩Allocated ⁦110%⁩ across all projectsR

Specialists

1 member

  • Haifa S. Al-RuwailiFinancial analyst⁦15%⁩C

Vendor team & advisers

1 member

    A AccountableR ResponsibleC ConsultedI Informed

    Stakeholders

    ⁦6⁩ stakeholders, ⁦4⁩ of them below the engagement needed

    Power / interest matrix

    Pick one to see how they are handled

    Power & influence

    Keep satisfied1

    high power, lower interest

    Manage closely4

    high power and interest

    Monitor0

    minimal effort

    Keep informed1

    high interest, lower power

    Eng. Turki A. Al-AnaziManage closelyEng. Bandar M. Al-ShammariManage closelyEnterprise PMOManage closelyEnd beneficiariesKeep informedFinancial Affairs AgencyKeep satisfiedUnited Water & Environment Co.Manage closely

    Interest

    Project sponsor

    Eng. Turki A. Al-Anazi

    Decisions and funding

    Influence

    Interest

    Engagement level

    Unaware

    Resistant

    Neutral

    Now

    Supportive

    Target

    Leading

    A gap of ⁦1⁩ steps — needs an engagement plan.

    Impact on the project
    Approves gates and changes
    Engagement plan
    Monthly briefing
    Last contact⁦2026-10-15⁩
    ⁦6⁩ results
    Export CSV
    OrganisationRoleActions
    Eng. Turki A. Al-AnaziProject sponsorDecisions and fundingSupportiveLeadingEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa⁦2026-10-15⁩
    Eng. Bandar M. Al-ShammariBusiness ownerAccepts deliverables, owns benefitsLeadingEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa⁦2026-10-18⁩
    Enterprise PMOGovernanceCompliance and data qualitySupportiveEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa⁦2026-10-12⁩
    Financial Affairs AgencyInternal departmentPayment approvalNeutralSupportiveHaifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@alwaha.gov.sa⁦2026-10-09⁩
    United Water & Environment Co.Main vendorDelivers the contracted workResistantSupportiveEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa⁦2026-10-19⁩
    End beneficiariesBeneficiariesUsers of the outcomeNeutralSupportiveEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa⁦2026-09-21⁩
    ⁦1⁩–⁦6⁩ of ⁦6⁩

    Communication plan

    Who needs what, when, through which channel, and who owns it.

    • Project sponsorStatus and decisions neededMonthlyMeetingEng. Waleed O. Al-Juhani⁦2026-11-10⁩
    • Business ownerDeliverable status and acceptance datesFortnightlyEmailEng. Waleed O. Al-Juhani⁦2026-10-29⁩
    • PMOData and indicator updatesWeeklyDashboardEng. Waleed O. Al-Juhani⁦2026-10-26⁩
    • BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Waleed O. Al-JuhaniAt launch

    Coming up

    By date

    1. 262026-10PMODashboard · Weekly
    2. 292026-10Business ownerEmail · Fortnightly
    3. 102026-11Project sponsorMeeting · Monthly