Dammam Administrative Courts Complex — Rehabilitation & Extension
Remove from watchlistRebuilding the existing complex of the Eastern Province administrative and appeal courts and adding a new wing with 28 courtrooms.
Budget (BAC)
Actual cost
81% of budget
Progress
Planned 92%
Estimate at completion
SAR +78.5M
SPI · CPI
Forecast finish
126 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control14 May 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionConditional goDate28 July 2023Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate4 March 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate2 April 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate20 June 2024Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate14 May 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+159 days vs approved
- Critical activities
- 5
- of 6 open activities
- Late activities
- 4
- past their baseline finish
- Schedule performance
- 0.68
- earned ÷ planned value
- Next milestone
- in 111 days
- Testing & acceptance complete
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
23 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 6 open activities, data date 2026-10-28
“Installation” needs a pace 15.4× faster than it has kept
It earned 20% in 389 days; the forecast assumes the rest in 101 days. At the pace so far it finishes on 2031-01-31.
Milestones slip 209 days on average — and it is getting worse
Each milestone’s slip in days, in date order; the later ones slip more than the early ones.
The critical chain
In date order, to final acceptance
Near-critical