BOG/2024/022
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
95% of the current value paid
Paid
53.2Mof a current value of SAR 56M
Value of each certificate
The last 14 — gross and net
Approved: 20
Count: 21 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 21October 2026 | 2026-10-25 | 1.5M | 145K | 145K | 174K | 1.3M | Submitted | |
| Certificate 20June 2026 | 2026-07-08 | 2.8M | 280K | 280K | 336K | 2.6M | Approved | |
| Certificate 19May 2026 | 2026-06-06 | 1.2M | 116K | 116K | 139.2K | 1.1M | Approved | |
| Certificate 18April 2026 | 2026-05-07 | 1.7M | 170K | 170K | 204K | 1.6M | Approved | |
| Certificate 17March 2026 | 2026-04-08 | 1.9M | 189K | 189K | 226.8K | 1.7M | Approved | |
| Certificate 16February 2026 | 2026-03-09 | 2.4M | 242K | 242K | 290.4K | 2.2M | Approved | |
| Certificate 15January 2026 | 2026-02-07 | 3M | 295K | 295K | 354K | 2.7M | Approved | |
| Certificate 14December 2025 | 2026-01-08 | 2.7M | 274K | 274K | 328.8K | 2.5M | Approved | |
| Certificate 13November 2025 | 2025-12-10 | 3.5M | 352K | 352K | 422.4K | 3.2M | Approved | |
| Certificate 12October 2025 | 2025-11-10 | 3.5M | 354K | 354K | 424.8K | 3.3M | Approved | |
| Certificate 11September 2025 | 2025-10-11 | 3.3M | 325K | 325K | 390K | 3M | Approved | |
| Certificate 10August 2025 | 2025-09-12 | 4M | 401K | 401K | 481.2K | 3.7M | Approved | |
| Certificate 9July 2025 | 2025-08-13 | 3.4M | 342K | 342K | 410.4K | 3.1M | Approved | |
| Certificate 8June 2025 | 2025-07-14 | 3.3M | 333K | 333K | 399.6K | 3.1M | Approved | |
| Certificate 7May 2025 | 2025-06-14 | 3.6M | 364K | 364K | 436.8K | 3.3M | Approved | |
| Certificate 6April 2025 | 2025-05-16 | 2.8M | 278K | 278K | 333.6K | 2.6M | Approved | |
| Certificate 5March 2025 | 2025-04-16 | 2.8M | 282K | 282K | 338.4K | 2.6M | Approved | |
| Certificate 4February 2025 | 2025-03-17 | 2.5M | 254K | 254K | 304.8K | 2.3M | Approved | |
| Certificate 3January 2025 | 2025-02-15 | 1.9M | 186K | 186K | 223.2K | 1.7M | Approved | |
| Certificate 2December 2024 | 2025-01-17 | 1.7M | 167K | 167K | 200.4K | 1.5M | Approved | |
| Certificate 1November 2024 | 2024-12-18 | 1.2M | 116K | 116K | 139.2K | 1.1M | Approved |