Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 8
- Date
- 2025-07-14
- Hijri
- 19 Muharram 1447 AH
- Reference
- PAY-2024-022-08
Interim payment certificate no. (8)
For the work of June 2025
- Contract number
- BOG/2024/022
- Etimad reference
- 2402550290
- Contract
- Abha administrative court — rehabilitation works
- Contractor
- United Buildings & Operations Co.
- Contractor VAT number
- 320510488360003
- Project
- Abha Administrative Court Rehabilitation
- Contract period
- 2024-11-03 — 2026-10-31
- Original contract value
- 56,000,000
- Current contract value
- 56,000,000
Certificate summary (SAR)
| 1 | Total value of work completed to date | 19,800,000 |
| 2 | Less: previous certificates | (16,470,000) |
| 3 | Value of work in this certificate | 3,330,000 |
| 4 | Less: retention (10%) | (333,000) |
| 5 | Less: advance payment recovery (10%) | (333,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (666,000) |
| 8 | Net before VAT | 2,664,000 |
| 9 | Add: value added tax (15%) | 399,600 |
| 10 | Net amount payable to the contractor | 3,063,600 |
Amount in words: Three million sixty-three thousand six hundred Saudi riyals only
Retention held up to this certificate: SAR 2M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 3,920,000 | 2,719,000 | 478,000 | 3,197,000 | 82% |
| Earthworks & foundations | 10,080,000 | 4,220,000 | 770,000 | 4,990,000 | 50% |
| Concrete & structural works | 17,360,000 | 5,610,000 | 1,142,000 | 6,752,000 | 39% |
| Mechanical, electrical & plumbing | 13,440,000 | 2,698,000 | 628,000 | 3,326,000 | 25% |
| Finishes & external works | 8,400,000 | 1,068,000 | 269,000 | 1,337,000 | 16% |
| Testing & commissioning | 2,800,000 | 155,000 | 43,000 | 198,000 | 7% |
| Total | 56,000,000 | 16,470,000 | 3,330,000 | 19,800,000 | 35% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Samer A. Al-Qahtani
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani