Board of GrievancesMunjaz10My actionsNotifications

Certificate ⁦8⁩ — June 2025

Abha administrative court — rehabilitation works

Kingdom of Saudi Arabia

Board of Grievances

General Directorate of Financial Affairs — Contracts & Procurement

Certificate no.
8
Date
⁦2025-07-14⁩
Hijri
19 Muharram 1447 AH
Reference
PAY-2024-022-08

Interim payment certificate no. (⁦8⁩)

For the work of June 2025

Contract number
BOG/2024/022
Etimad reference
2402550290
Contract
Abha administrative court — rehabilitation works
Contractor
United Buildings & Operations Co.
Contractor VAT number
320510488360003
Project
Abha Administrative Court Rehabilitation
Contract period
⁦2024-11-03⁩ — ⁦2026-10-31⁩
Original contract value
56,000,000
Current contract value
56,000,000

Certificate summary (SAR)

1Total value of work completed to date19,800,000
2Less: previous certificates(16,470,000)
3Value of work in this certificate3,330,000
4Less: retention (⁦10%⁩)(333,000)
5Less: advance payment recovery (⁦10%⁩)(333,000)
6Less: delay and breach penalties0
7Total deductions(666,000)
8Net before VAT2,664,000
9Add: value added tax (15%)399,600
10Net amount payable to the contractor3,063,600

Amount in words: Three million sixty-three thousand six hundred Saudi riyals only

Retention held up to this certificate: SAR 2M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation3,920,0002,719,000478,0003,197,000⁦82%⁩
Earthworks & foundations10,080,0004,220,000770,0004,990,000⁦50%⁩
Concrete & structural works17,360,0005,610,0001,142,0006,752,000⁦39%⁩
Mechanical, electrical & plumbing13,440,0002,698,000628,0003,326,000⁦25%⁩
Finishes & external works8,400,0001,068,000269,0001,337,000⁦16%⁩
Testing & commissioning2,800,000155,00043,000198,000⁦7%⁩
Total56,000,00016,470,0003,330,00019,800,000⁦35%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Samer A. Al-Qahtani

Al-Qahtani⁦2025-07-14⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2025-07-16⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2025-07-19⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-07-22⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2025-07-25⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-07-14⁩

    Eng. Samer A. Al-Qahtani

  2. Engineer verifies quantities⁦2025-07-16⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2025-07-19⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2025-07-22⁩

    Khalid N. Al-Mutairi · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-07-25⁩

    Dr. Abdullah S. Al-Qahtani · President of the Board of Grievances

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

25 July 2025

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2025-07-25 13:00

22 July 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-07-22 13:00

19 July 2025

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2025-07-19 13:00

16 July 2025

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2025-07-16 13:00

14 July 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-07-14 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close