10My actionsNotifications

Certificate ⁦20⁩ — June 2026

Small dams & recharge channels — construction

Kingdom of Saudi Arabia

Al-Waha Region Development Authority

General Directorate of Contracts & Finance

Certificate no.
20
Date
⁦2026-07-08⁩
Hijri
23 Muharram 1448 AH
Reference
PAY-2026-001

Interim payment certificate no. (⁦20⁩)

For the work of June 2026

Contract number
WRDA/2024/022
Etimad reference
2402550290
Contract
Small dams & recharge channels — construction
Contractor
United Water & Environment Co.
Contractor VAT number
320510488360003
Project
Rainwater Harvesting & Small Dams
Contract period
⁦2024-11-03⁩ — ⁦2026-10-31⁩
Original contract value
56,000,000
Current contract value
56,000,000

Certificate summary (SAR)

1Total value of work completed to date53,200,000
2Less: previous certificates(50,400,000)
3Value of work in this certificate2,800,000
4Less: retention (⁦10%⁩)(280,000)
5Less: advance payment recovery (⁦10%⁩)(280,000)
6Less: delay and breach penalties0
7Total deductions(560,000)
8Net before VAT2,240,000
9Add: value added tax (15%)336,000
10Net amount payable to the contractor2,576,000

Amount in words: Two million five hundred seventy-six thousand Saudi riyals only

Retention held up to this certificate: SAR 5.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation3,920,0003,858,00062,0003,920,000⁦100%⁩
Earthworks & foundations10,080,0009,866,000214,00010,080,000⁦100%⁩
Concrete & structural works17,360,00016,604,000756,00017,360,000⁦100%⁩
Mechanical, electrical & plumbing13,440,00012,454,000986,00013,440,000⁦100%⁩
Finishes & external works8,400,0007,144,000724,0007,868,000⁦94%⁩
Testing & commissioning2,800,000474,00058,000532,000⁦19%⁩
Total56,000,00050,400,0002,800,00053,200,000⁦95%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Samer A. Al-Qahtani

Al-Qahtani⁦2026-07-08⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-07-10⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2026-07-13⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-07-16⁩

Authority holder

Eng. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-07-19⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-07-08⁩

    Eng. Samer A. Al-Qahtani

  2. Engineer verifies quantities⁦2026-07-10⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-07-13⁩

    Eng. Waleed O. Al-Juhani · Director, Utilities & Public Services

    Took 3 days

  4. Payment order prepared⁦2026-07-16⁩

    Khalid N. Al-Mutairi · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-07-19⁩

    Eng. Abdullah S. Al-Qahtani · Chief Executive Officer

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Eng. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Eng. Abdullah S. Al-Qahtani

Certificate history

19 July 2026

  1. Payment: Eng. Abdullah S. Al-Qahtani signed “Final approval”

    2026-07-19 13:00

16 July 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-07-16 13:00

13 July 2026

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2026-07-13 13:00

10 July 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-07-10 13:00

8 July 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-07-08 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close