Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 16
- Date
- 2026-03-09
- Hijri
- 20 Ramadan 1447 AH
- Reference
- PAY-2024-022-16
Interim payment certificate no. (16)
For the work of February 2026
- Contract number
- BOG/2024/022
- Etimad reference
- 2402550290
- Contract
- Abha administrative court — rehabilitation works
- Contractor
- United Buildings & Operations Co.
- Contractor VAT number
- 320510488360003
- Project
- Abha Administrative Court Rehabilitation
- Contract period
- 2024-11-03 — 2026-10-31
- Original contract value
- 56,000,000
- Current contract value
- 56,000,000
Certificate summary (SAR)
| 1 | Total value of work completed to date | 45,650,000 |
| 2 | Less: previous certificates | (43,230,000) |
| 3 | Value of work in this certificate | 2,420,000 |
| 4 | Less: retention (10%) | (242,000) |
| 5 | Less: advance payment recovery (10%) | (242,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (484,000) |
| 8 | Net before VAT | 1,936,000 |
| 9 | Add: value added tax (15%) | 290,400 |
| 10 | Net amount payable to the contractor | 2,226,400 |
Amount in words: Two million two hundred twenty-six thousand four hundred Saudi riyals only
Retention held up to this certificate: SAR 4.6M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 3,920,000 | 3,814,000 | 106,000 | 3,920,000 | 100% |
| Earthworks & foundations | 10,080,000 | 9,749,000 | 331,000 | 10,080,000 | 100% |
| Concrete & structural works | 17,360,000 | 16,487,000 | 873,000 | 17,360,000 | 100% |
| Mechanical, electrical & plumbing | 13,440,000 | 9,960,000 | 792,000 | 10,752,000 | 80% |
| Finishes & external works | 8,400,000 | 2,809,000 | 272,000 | 3,081,000 | 37% |
| Testing & commissioning | 2,800,000 | 411,000 | 46,000 | 457,000 | 16% |
| Total | 56,000,000 | 43,230,000 | 2,420,000 | 45,650,000 | 82% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Samer A. Al-Qahtani
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani