Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 19
- Date
- 2026-06-06
- Hijri
- 20 Dhuʻl-Hijjah 1447 AH
- Reference
- PAY-2024-022-19
Interim payment certificate no. (19)
For the work of May 2026
- Contract number
- BOG/2024/022
- Etimad reference
- 2402550290
- Contract
- Abha administrative court — rehabilitation works
- Contractor
- United Buildings & Operations Co.
- Contractor VAT number
- 320510488360003
- Project
- Abha Administrative Court Rehabilitation
- Contract period
- 2024-11-03 — 2026-10-31
- Original contract value
- 56,000,000
- Current contract value
- 56,000,000
Certificate summary (SAR)
| 1 | Total value of work completed to date | 50,400,000 |
| 2 | Less: previous certificates | (49,240,000) |
| 3 | Value of work in this certificate | 1,160,000 |
| 4 | Less: retention (10%) | (116,000) |
| 5 | Less: advance payment recovery (10%) | (116,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (232,000) |
| 8 | Net before VAT | 928,000 |
| 9 | Add: value added tax (15%) | 139,200 |
| 10 | Net amount payable to the contractor | 1,067,200 |
Amount in words: One million sixty-seven thousand two hundred Saudi riyals only
Retention held up to this certificate: SAR 5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 3,920,000 | 3,887,000 | 33,000 | 3,920,000 | 100% |
| Earthworks & foundations | 10,080,000 | 9,966,000 | 114,000 | 10,080,000 | 100% |
| Concrete & structural works | 17,360,000 | 17,007,000 | 353,000 | 17,360,000 | 100% |
| Mechanical, electrical & plumbing | 13,440,000 | 13,006,000 | 434,000 | 13,440,000 | 100% |
| Finishes & external works | 8,400,000 | 4,893,000 | 203,000 | 5,096,000 | 61% |
| Testing & commissioning | 2,800,000 | 481,000 | 23,000 | 504,000 | 18% |
| Total | 56,000,000 | 49,240,000 | 1,160,000 | 50,400,000 | 90% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Samer A. Al-Qahtani
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani