Board of GrievancesMunjaz10My actionsNotifications

Certificate ⁦19⁩ — May 2026

Abha administrative court — rehabilitation works

Kingdom of Saudi Arabia

Board of Grievances

General Directorate of Financial Affairs — Contracts & Procurement

Certificate no.
19
Date
⁦2026-06-06⁩
Hijri
20 Dhuʻl-Hijjah 1447 AH
Reference
PAY-2024-022-19

Interim payment certificate no. (⁦19⁩)

For the work of May 2026

Contract number
BOG/2024/022
Etimad reference
2402550290
Contract
Abha administrative court — rehabilitation works
Contractor
United Buildings & Operations Co.
Contractor VAT number
320510488360003
Project
Abha Administrative Court Rehabilitation
Contract period
⁦2024-11-03⁩ — ⁦2026-10-31⁩
Original contract value
56,000,000
Current contract value
56,000,000

Certificate summary (SAR)

1Total value of work completed to date50,400,000
2Less: previous certificates(49,240,000)
3Value of work in this certificate1,160,000
4Less: retention (⁦10%⁩)(116,000)
5Less: advance payment recovery (⁦10%⁩)(116,000)
6Less: delay and breach penalties0
7Total deductions(232,000)
8Net before VAT928,000
9Add: value added tax (15%)139,200
10Net amount payable to the contractor1,067,200

Amount in words: One million sixty-seven thousand two hundred Saudi riyals only

Retention held up to this certificate: SAR 5M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation3,920,0003,887,00033,0003,920,000⁦100%⁩
Earthworks & foundations10,080,0009,966,000114,00010,080,000⁦100%⁩
Concrete & structural works17,360,00017,007,000353,00017,360,000⁦100%⁩
Mechanical, electrical & plumbing13,440,00013,006,000434,00013,440,000⁦100%⁩
Finishes & external works8,400,0004,893,000203,0005,096,000⁦61%⁩
Testing & commissioning2,800,000481,00023,000504,000⁦18%⁩
Total56,000,00049,240,0001,160,00050,400,000⁦90%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Samer A. Al-Qahtani

Al-Qahtani⁦2026-06-06⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-06-08⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2026-06-11⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-06-14⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-06-17⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-06-06⁩

    Eng. Samer A. Al-Qahtani

  2. Engineer verifies quantities⁦2026-06-08⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-06-11⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2026-06-14⁩

    Khalid N. Al-Mutairi · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-06-17⁩

    Dr. Abdullah S. Al-Qahtani · President of the Board of Grievances

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

17 June 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-06-17 13:00

14 June 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-06-14 13:00

11 June 2026

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2026-06-11 13:00

8 June 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-06-08 13:00

6 June 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-06-06 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close