Certificate ⁦21⁩ — October 2026

Abha administrative court — rehabilitation works

Kingdom of Saudi Arabia

Board of Grievances

General Directorate of Financial Affairs — Contracts & Procurement

Certificate no.
21
Date
⁦2026-10-25⁩
Hijri
14 Jumada I 1448 AH
Reference
PAY-2026-024

Interim payment certificate no. (⁦21⁩)

For the work of October 2026

Contract number
BOG/2024/022
Etimad reference
2402550290
Contract
Abha administrative court — rehabilitation works
Contractor
United Buildings & Operations Co.
Contractor VAT number
320510488360003
Project
Abha Administrative Court Rehabilitation
Contract period
⁦2024-11-03⁩ — ⁦2026-10-31⁩
Original contract value
56,000,000
Current contract value
56,000,000

Certificate summary (SAR)

1Total value of work completed to date54,650,000
2Less: previous certificates(53,200,000)
3Value of work in this certificate1,450,000
4Less: retention (⁦10%⁩)(145,000)
5Less: advance payment recovery (⁦10%⁩)(145,000)
6Less: delay and breach penalties0
7Total deductions(290,000)
8Net before VAT1,160,000
9Add: value added tax (15%)174,000
10Net amount payable to the contractor1,334,000

Amount in words: One million three hundred thirty-four thousand Saudi riyals only

Retention held up to this certificate: SAR 5.5M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation3,920,0003,889,00031,0003,920,000⁦100%⁩
Earthworks & foundations10,080,0009,986,00094,00010,080,000⁦100%⁩
Concrete & structural works17,360,00016,996,000364,00017,360,000⁦100%⁩
Mechanical, electrical & plumbing13,440,00012,949,000491,00013,440,000⁦100%⁩
Finishes & external works8,400,0008,011,000389,0008,400,000⁦100%⁩
Testing & commissioning2,800,0001,369,00081,0001,450,000⁦52%⁩
Total56,000,00053,200,0001,450,00054,650,000⁦98%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Samer A. Al-Qahtani

Al-Qahtani⁦2026-10-25⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Awaiting signature

Project manager

Eng. Waleed O. Al-Juhani

Later

Finance & contracts

Khalid N. Al-Mutairi

Later

Authority holder

Dr. Abdullah S. Al-Qahtani

Later
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Current step: Engineer verifies quantities

  1. Certificate submitted⁦2026-10-25⁩

    Eng. Samer A. Al-Qahtani

  2. Engineer verifies quantitiesIn 2 days2026-10-3019 Jumada I 1448 AH

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Waiting for Eng. Ibrahim A. Al-Ghamdi
  3. Project manager certifies

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

  4. Payment order prepared

    Khalid N. Al-Mutairi · Senior Finance & Contracts SpecialistPayment request creator

  5. Final approval

    Dr. Abdullah S. Al-Qahtani · President of the Board of Grievances

You are viewing as Dr. Noura M. Al-Otaibi

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

25 October 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-10-25 09:00