Judicial Innovation Lab («Ebtikar»)
Add to watchlistA sandbox to pilot judicial-tech solutions with universities and start-ups before rolling them out to the courts.
Budget (BAC)
Actual cost
0% of budget
Progress
Planned 0%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
IdeaPhase 1 of 11
Next gate:Feasibility15 August 2026
- Idea · Current phaseIdea · Current phase
- Gate into «Feasibility»DecisionNot held yetDate15 August 2026Feasibility · Not startedFeasibility · Not started
- Gate into «Initiation»DecisionNot held yetInitiation · Not startedInitiation · Not started
- Gate into «Planning»DecisionNot held yetPlanning · Not startedPlanning · Not started
- Gate into «Approval»DecisionNot held yetApproval · Not startedApproval · Not started
- Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
- Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Closure readiness
Closure planned after the forecast finish on 2027-12-31
A preview of what closure will need, with the planned dates, and the lessons captured so far.
Closure checklist
Seven mandatory items before any project closes.
- 1
Deliverables acceptedNot started
Final acceptance of every deliverable
Faisal A. Al-ShehriPlanned 2027-12-21
- 2
Financial closureNot started
Spend reconciled, commitments closed
Khalid N. Al-MutairiPlanned 2028-01-20
- 3
Contract closureNot started
Contracts closed, retention released
Khalid N. Al-MutairiPlanned 2028-01-30
- 4
Documents archivedNot started
Documents archived with classification
Rahaf I. Al-NefaiePlanned 2028-01-25
- 5
Lessons learnedNot started
Lessons-learned session
Rahaf I. Al-NefaiePlanned 2028-01-15
- 6
Benefits owner assignedNot started
Benefits handed to their owner with a measurement plan
Faisal A. Al-ShehriPlanned 2028-01-10
- 7
Final report approvedNot started
Final report and its approval
Rahaf I. Al-NefaiePlanned 2028-02-04
Post-implementation review
Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?
The review comes after closure
About three months after the forecast finish (2027-12-31), with the sponsor and the benefits owner.
Lessons learned
0 lessons — offered automatically to similar projects when they are created.
No lessons captured yet
Capture what the team learned during delivery; closure needs at least one.
Benefits handover
Each benefit moves from the project manager to an owner who measures it after closure.
No benefits recorded for this project.