Judicial Innovation Lab («Ebtikar»)
Add to watchlistA sandbox to pilot judicial-tech solutions with universities and start-ups before rolling them out to the courts.
Budget (BAC)
Actual cost
0% of budget
Progress
Planned 0%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
IdeaPhase 1 of 11
Next gate:Feasibility15 August 2026
- Idea · Current phaseIdea · Current phase
- Gate into «Feasibility»DecisionNot held yetDate15 August 2026Feasibility · Not startedFeasibility · Not started
- Gate into «Initiation»DecisionNot held yetInitiation · Not startedInitiation · Not started
- Gate into «Planning»DecisionNot held yetPlanning · Not startedPlanning · Not started
- Gate into «Approval»DecisionNot held yetApproval · Not startedApproval · Not started
- Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
- Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Project lifecycle and its gates
Current phase: Idea. Pick a gate on the track to review it.
- Gate into «Feasibility»DecisionNot held yetDate15 August 2026IdeaCurrent phaseCurrent phase
- Gate into «Initiation»DecisionNot held yet2FeasibilityNot started
- Gate into «Planning»DecisionNot held yet3InitiationNot started
- Gate into «Approval»DecisionNot held yet4PlanningNot started
- Gate into «Procurement»DecisionNot held yet5ApprovalNot started
- Gate into «Execution»DecisionNot held yet6ProcurementNot started
- Gate into «Monitoring & Control»DecisionNot held yet7ExecutionNot started
- Gate into «Handover»DecisionNot held yet8Monitoring & ControlNot started
- Gate into «Closure»DecisionNot held yet9HandoverNot started
- Gate into «Benefits Realization»DecisionNot held yet10ClosureNot started
- 11Benefits RealizationNot started
Idea gate — into feasibility
Gate readiness
Enough for a conditional go only
Automated control: no move until the criteria are met
- 1 mandatory checklist item open
- 1 required document not approved
- 1 mandatory criterion under 70 points
- Weighted score 73 under the pass mark 75
Checklist
3 of 4 done
- Need and problem statement writtenMandatory
- Requesting unit and beneficiaries namedMandatory
- Rough cost estimate (±50%)Mandatory
- No overlap with an existing project
Required documents
0 of 1 approved
- Project request formNot submitted
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Strategic alignmentweight 40%Met
Awaiting evidence from the project team.
Clarity of needweight 30%Not met
Awaiting evidence from the project team.
Priority against other demandsweight 30%
Awaiting evidence from the project team.
Approvers
EPMO Committee
- Dr. Noura M. Al-OtaibiEPMO directorVote pending
- Eng. Majed S. Al-RasheedProject sponsorVote pending
- Faisal A. Al-ShehriBusiness ownerVote pending