Arar Administrative Courts Complex
Add to watchlistA complex for the Northern Borders administrative court on land allocated by the municipality, with utilities and access roads.
Budget (BAC)
Actual cost
34% of budget
Progress
Planned 37%
Estimate at completion
SAR +9.9M
SPI · CPI
Forecast finish
28 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control13 May 2027
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate17 January 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate14 August 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate7 September 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate9 November 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate13 May 2027Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth