PRJ-2026-034At risk7ExecutionConstruction

Arar Administrative Courts Complex

Add to watchlist

A complex for the Northern Borders administrative court on land allocated by the municipality, with utilities and access roads.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 238M

Actual cost

SAR 81.8M

⁦34%⁩ of budget

Progress

⁦33%⁩

Planned ⁦37%⁩

Estimate at completion

SAR 247.9M

SAR +9.9M

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control13 May 2027

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate17 January 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate14 August 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate7 September 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate13 May 2027Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+27⁩ days vs approved

Original baseline⁦2027-08-31⁩
Approved baseline⁦2027-08-31⁩
Current forecast⁦2027-09-27⁩
By earned schedule⁦2028-12-15⁩
Critical activities
8
of ⁦10⁩ open activities
Late activities
7
past their baseline finish
Schedule performance
0.49
earned ÷ planned value
Next milestone
in 124 days
Build complete
Expand allCollapse all
Activity
Arar Administrative Courts ComplexPlanned: ⁦2025-07-06⁩ → ⁦2027-08-31⁩Forecast: ⁦2025-07-06⁩ → ⁦2027-09-27⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-07-06⁩ → ⁦2025-12-15⁩Actual: ⁦2025-07-06⁩ → ⁦2026-02-14⁩
Project plan & baselinePlanned: ⁦2025-07-06⁩ → ⁦2025-10-14⁩Actual: ⁦2025-07-06⁩ → ⁦2025-11-20⁩
Monitoring & reportingPlanned: ⁦2025-09-06⁩ → ⁦2025-12-15⁩Actual: ⁦2025-09-30⁩ → ⁦2026-02-14⁩
Project plan approvedPlanned: ⁦2025-12-15⁩ → ⁦2025-12-15⁩Actual: ⁦2026-02-14⁩ → ⁦2026-02-14⁩Project plan approved
Design & permitsPlanned: ⁦2025-11-08⁩ → ⁦2026-04-19⁩Actual: ⁦2025-12-24⁩ → ⁦2026-08-04⁩
Detailed designPlanned: ⁦2025-11-08⁩ → ⁦2026-02-16⁩Actual: ⁦2025-12-24⁩ → ⁦2026-05-10⁩
Permits & approvalsPlanned: ⁦2026-01-09⁩ → ⁦2026-04-19⁩Actual: ⁦2026-03-20⁩ → ⁦2026-08-04⁩
Designs approvedPlanned: ⁦2026-04-19⁩ → ⁦2026-04-19⁩Actual: ⁦2026-08-04⁩ → ⁦2026-08-04⁩Designs approved
Civil worksPlanned: ⁦2026-03-13⁩ → ⁦2026-10-23⁩Forecast: ⁦2026-05-14⁩ → ⁦2027-03-01⁩Float: ⁦0⁩d
Site works & excavationPlanned: ⁦2026-03-13⁩ → ⁦2026-06-20⁩Actual: ⁦2026-06-13⁩ → ⁦2026-10-26⁩
StructurePlanned: ⁦2026-05-14⁩ → ⁦2026-08-22⁩Forecast: ⁦2026-05-14⁩ → ⁦2027-01-18⁩Float: ⁦0⁩d+149
FinishesPlanned: ⁦2026-07-15⁩ → ⁦2026-10-23⁩Forecast: ⁦2026-12-24⁩ → ⁦2027-03-01⁩Float: ⁦0⁩d+129
Build completePlanned: ⁦2026-10-23⁩ → ⁦2026-10-23⁩Forecast: ⁦2027-03-01⁩ → ⁦2027-03-01⁩Float: ⁦210⁩dBuild complete
MEP worksPlanned: ⁦2026-09-16⁩ → ⁦2027-04-28⁩Forecast: ⁦2027-02-04⁩ → ⁦2027-07-05⁩Float: ⁦0⁩d
SupplyPlanned: ⁦2026-09-16⁩ → ⁦2026-12-24⁩Forecast: ⁦2027-02-04⁩ → ⁦2027-04-12⁩Float: ⁦0⁩d+109
InstallationPlanned: ⁦2026-11-17⁩ → ⁦2027-02-25⁩Forecast: ⁦2027-03-18⁩ → ⁦2027-05-24⁩Float: ⁦0⁩d+88
Testing & commissioningPlanned: ⁦2027-01-18⁩ → ⁦2027-04-28⁩Forecast: ⁦2027-04-29⁩ → ⁦2027-07-05⁩Float: ⁦0⁩d+68
Testing & acceptance completePlanned: ⁦2027-04-28⁩ → ⁦2027-04-28⁩Forecast: ⁦2027-07-05⁩ → ⁦2027-07-05⁩Float: ⁦84⁩dTesting & acceptance complete
HandoverPlanned: ⁦2027-03-22⁩ → ⁦2027-08-31⁩Forecast: ⁦2027-06-10⁩ → ⁦2027-09-27⁩Float: ⁦0⁩d
Provisional acceptancePlanned: ⁦2027-03-22⁩ → ⁦2027-06-30⁩Forecast: ⁦2027-06-10⁩ → ⁦2027-08-16⁩Float: ⁦0⁩d+47
Final acceptancePlanned: ⁦2027-05-23⁩ → ⁦2027-08-31⁩Forecast: ⁦2027-07-22⁩ → ⁦2027-09-27⁩Float: ⁦0⁩d+27
Final handoverPlanned: ⁦2027-08-31⁩ → ⁦2027-08-31⁩Forecast: ⁦2027-09-27⁩ → ⁦2027-09-27⁩Float: ⁦0⁩dFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦23⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦10⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦7⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Structure” needs a pace ⁦9.3⁩× faster than it has kept

It earned ⁦18%⁩ in 167 days; the forecast assumes the rest in 82 days. At the pace so far it finishes on ⁦2028-11-27⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 99 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

61
107
129
G1G2G3

The critical chain

In date order, to final acceptance