Remote Video Hearings Roll-out — Makkah Region
Add to watchlistEquip 180 courtrooms and circuit offices in Jeddah, Makkah and Taif for video hearings with secure recording.
Budget (BAC)
Actual cost
2% of budget
Progress
Planned 2%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ApprovalPhase 5 of 11
Next gate:Procurement20 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionConditional goDate13 February 2026Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 August 2026Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate1 September 2026Approval · Current phaseApproval · Current phase
- Gate into «Procurement»DecisionNot held yetDate20 September 2026Procurement · Not startedProcurement · Not started
- Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+2 days vs approved
- Critical activities
- 12
- of 17 open activities
- Late activities
- 12
- past their baseline finish
- Schedule performance
- 0.33
- earned ÷ planned value
- Next milestone
- in 72 days
- Project plan approved
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
23 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 17 open activities, data date 2026-10-28
The critical chain
In date order, to final acceptance
Near-critical