Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-012On track7ExecutionAgile

Judicial Indicators Dashboard & Performance Measurement

Add to watchlist

Judicial and institutional KPIs — time to judgment, appeal outcomes, video hearings — wired to automated scorecards down to circuit level.

Budget (BAC)

SAR 9.8M

Actual cost

SAR 7.4M

⁦76%⁩ of budget

Progress

⁦76%⁩

Planned ⁦75%⁩

Estimate at completion

SAR 9.8M

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control25 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate21 March 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate1 October 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate15 October 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate23 November 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate25 October 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+23⁩ days vs approved

Original baseline⁦2026-12-31⁩
Approved baseline⁦2026-12-31⁩
Current forecast⁦2027-01-23⁩
By earned schedule⁦2027-05-16⁩
Critical activities
4
of ⁦5⁩ open activities
Late activities
3
past their baseline finish
Schedule performance
0.79
earned ÷ planned value
Next milestone
in 67 days
Testing & acceptance complete
Expand allCollapse all
Activity
Judicial Indicators Dashboard & Performance MeasurementPlanned: ⁦2025-09-07⁩ → ⁦2026-12-31⁩Forecast: ⁦2025-09-07⁩ → ⁦2027-01-23⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-09-07⁩ → ⁦2026-01-03⁩Actual: ⁦2025-09-07⁩ → ⁦2026-01-27⁩
Project plan & baselinePlanned: ⁦2025-09-07⁩ → ⁦2025-11-18⁩Actual: ⁦2025-09-07⁩ → ⁦2025-12-04⁩
Monitoring & reportingPlanned: ⁦2025-10-22⁩ → ⁦2026-01-03⁩Actual: ⁦2025-11-01⁩ → ⁦2026-01-27⁩
Project plan approvedPlanned: ⁦2026-01-03⁩ → ⁦2026-01-03⁩Actual: ⁦2026-01-27⁩ → ⁦2026-01-27⁩Project plan approved
DiagnosisPlanned: ⁦2025-12-07⁩ → ⁦2026-04-03⁩Actual: ⁦2025-12-26⁩ → ⁦2026-05-17⁩
Current-state assessmentPlanned: ⁦2025-12-07⁩ → ⁦2026-02-17⁩Actual: ⁦2025-12-26⁩ → ⁦2026-03-23⁩
BenchmarkingPlanned: ⁦2026-01-21⁩ → ⁦2026-04-03⁩Actual: ⁦2026-02-18⁩ → ⁦2026-05-17⁩
Designs approvedPlanned: ⁦2026-04-03⁩ → ⁦2026-04-03⁩Actual: ⁦2026-05-17⁩ → ⁦2026-05-17⁩Designs approved
DesignPlanned: ⁦2026-03-07⁩ → ⁦2026-07-03⁩Actual: ⁦2026-04-14⁩ → ⁦2026-09-03⁩
Target modelPlanned: ⁦2026-03-07⁩ → ⁦2026-05-19⁩Actual: ⁦2026-04-14⁩ → ⁦2026-07-11⁩
RoadmapPlanned: ⁦2026-04-21⁩ → ⁦2026-07-03⁩Actual: ⁦2026-06-08⁩ → ⁦2026-09-03⁩
Build completePlanned: ⁦2026-07-03⁩ → ⁦2026-07-03⁩Actual: ⁦2026-09-03⁩ → ⁦2026-09-03⁩Build complete
ImplementationPlanned: ⁦2026-06-06⁩ → ⁦2026-10-01⁩Forecast: ⁦2026-07-21⁩ → ⁦2027-01-03⁩Float: ⁦0⁩d
Wave 1Planned: ⁦2026-06-06⁩ → ⁦2026-08-17⁩Actual: ⁦2026-08-02⁩ → ⁦2026-10-26⁩
Wave 2Planned: ⁦2026-07-21⁩ → ⁦2026-10-01⁩Forecast: ⁦2026-07-21⁩ → ⁦2027-01-03⁩Float: ⁦0⁩d+94
Testing & acceptance completePlanned: ⁦2026-10-01⁩ → ⁦2026-10-01⁩Forecast: ⁦2027-01-03⁩ → ⁦2027-01-03⁩Float: ⁦20⁩dTesting & acceptance complete
Handover & knowledge transferPlanned: ⁦2026-09-04⁩ → ⁦2026-12-31⁩Forecast: ⁦2026-12-28⁩ → ⁦2027-01-23⁩Float: ⁦0⁩d
Knowledge transferPlanned: ⁦2026-09-04⁩ → ⁦2026-11-16⁩Forecast: ⁦2026-12-28⁩ → ⁦2027-01-13⁩Float: ⁦0⁩d+58
Final reportPlanned: ⁦2026-10-20⁩ → ⁦2026-12-31⁩Forecast: ⁦2027-01-07⁩ → ⁦2027-01-23⁩Float: ⁦0⁩d+23
Final handoverPlanned: ⁦2026-12-31⁩ → ⁦2026-12-31⁩Forecast: ⁦2027-01-23⁩ → ⁦2027-01-23⁩Float: ⁦0⁩dFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦21⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦5⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦3⁩ activities with no float

Every day lost on this chain is a day lost at launch. ⁦1⁩ more activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Wave 2” needs a pace ⁦19.6⁩× faster than it has kept

It earned ⁦7%⁩ in 99 days; the forecast assumes the rest in 67 days. At the pace so far it finishes on ⁦2030-06-04⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 49 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

24
44
62
94
23
G1G2G3G4G5

The critical chain

In date order, to final acceptance

Near-critical

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close