PRJ-2026-035On track1IdeaAgile

Judicial Innovation Lab («Ebtikar»)

Add to watchlist

A sandbox to pilot judicial-tech solutions with universities and start-ups before rolling them out to the courts.

Project managerRahaf I. Al-NefaieSponsorEng. Majed S. Al-Rasheed

Budget (BAC)

SAR 5.2M

Actual cost

SAR 0

⁦0%⁩ of budget

Progress

⁦0%⁩

Planned ⁦0%⁩

Estimate at completion

SAR 5.2M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

IdeaPhase ⁦1⁩ of ⁦11⁩

Next gate:Feasibility15 August 2026

  1. Idea · Current phaseIdea · Current phase
  2. Gate into «Feasibility»DecisionNot held yetDate15 August 2026Feasibility · Not startedFeasibility · Not started
  3. Gate into «Initiation»DecisionNot held yetInitiation · Not startedInitiation · Not started
  4. Gate into «Planning»DecisionNot held yetPlanning · Not startedPlanning · Not started
  5. Gate into «Approval»DecisionNot held yetApproval · Not startedApproval · Not started
  6. Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+123⁩ days vs approved

Original baseline⁦2027-12-31⁩
Approved baseline⁦2027-12-31⁩
Current forecast⁦2028-05-02⁩
By earned schedule⁦2030-02-15⁩
Critical activities
11
of ⁦15⁩ open activities
Late activities
10
past their baseline finish
Schedule performance
0.00
earned ÷ planned value
Next milestone
in 208 days
Project plan approved
Expand allCollapse all
Activity
Judicial Innovation Lab («Ebtikar»)Planned: ⁦2027-02-01⁩ → ⁦2027-12-31⁩Forecast: ⁦2027-02-01⁩ → ⁦2028-05-02⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2027-02-01⁩ → ⁦2027-04-24⁩Forecast: ⁦2027-02-01⁩ → ⁦2027-05-24⁩Float: ⁦0⁩d
Project plan & baselinePlanned: ⁦2027-02-01⁩ → ⁦2027-03-23⁩Forecast: ⁦2027-02-01⁩ → ⁦2027-04-11⁩Float: ⁦0⁩d+19
Monitoring & reportingPlanned: ⁦2027-03-04⁩ → ⁦2027-04-24⁩Forecast: ⁦2027-03-16⁩ → ⁦2027-05-24⁩Float: ⁦0⁩d+30
Project plan approvedPlanned: ⁦2027-04-24⁩ → ⁦2027-04-24⁩Forecast: ⁦2027-05-24⁩ → ⁦2027-05-24⁩Float: ⁦344⁩dProject plan approved
DiagnosisPlanned: ⁦2027-04-05⁩ → ⁦2027-06-26⁩Forecast: ⁦2027-04-28⁩ → ⁦2027-08-18⁩Float: ⁦0⁩d
Current-state assessmentPlanned: ⁦2027-04-05⁩ → ⁦2027-05-25⁩Forecast: ⁦2027-04-28⁩ → ⁦2027-07-06⁩Float: ⁦0⁩d+42
BenchmarkingPlanned: ⁦2027-05-06⁩ → ⁦2027-06-26⁩Forecast: ⁦2027-06-10⁩ → ⁦2027-08-18⁩Float: ⁦0⁩d+53
Designs approvedPlanned: ⁦2027-06-26⁩ → ⁦2027-06-26⁩Forecast: ⁦2027-08-18⁩ → ⁦2027-08-18⁩Float: ⁦258⁩dDesigns approved
DesignPlanned: ⁦2027-06-07⁩ → ⁦2027-08-27⁩Forecast: ⁦2027-07-23⁩ → ⁦2027-11-12⁩Float: ⁦0⁩d
Target modelPlanned: ⁦2027-06-07⁩ → ⁦2027-07-27⁩Forecast: ⁦2027-07-23⁩ → ⁦2027-09-30⁩Float: ⁦0⁩d+65
RoadmapPlanned: ⁦2027-07-08⁩ → ⁦2027-08-27⁩Forecast: ⁦2027-09-04⁩ → ⁦2027-11-12⁩Float: ⁦0⁩d+77
Build completePlanned: ⁦2027-08-27⁩ → ⁦2027-08-27⁩Forecast: ⁦2027-11-12⁩ → ⁦2027-11-12⁩Float: ⁦172⁩dBuild complete
ImplementationPlanned: ⁦2027-08-08⁩ → ⁦2027-10-29⁩Forecast: ⁦2027-10-17⁩ → ⁦2028-02-06⁩Float: ⁦0⁩d
Wave 1Planned: ⁦2027-08-08⁩ → ⁦2027-09-28⁩Forecast: ⁦2027-10-17⁩ → ⁦2027-12-25⁩Float: ⁦0⁩d+88
Wave 2Planned: ⁦2027-09-09⁩ → ⁦2027-10-29⁩Forecast: ⁦2027-11-29⁩ → ⁦2028-02-06⁩Float: ⁦0⁩d+100
Testing & acceptance completePlanned: ⁦2027-10-29⁩ → ⁦2027-10-29⁩Forecast: ⁦2028-02-06⁩ → ⁦2028-02-06⁩Float: ⁦86⁩dTesting & acceptance complete
Handover & knowledge transferPlanned: ⁦2027-10-10⁩ → ⁦2027-12-31⁩Forecast: ⁦2028-01-11⁩ → ⁦2028-05-02⁩Float: ⁦0⁩d
Knowledge transferPlanned: ⁦2027-10-10⁩ → ⁦2027-11-30⁩Forecast: ⁦2028-01-11⁩ → ⁦2028-03-20⁩Float: ⁦0⁩d+111
Final reportPlanned: ⁦2027-11-11⁩ → ⁦2027-12-31⁩Forecast: ⁦2028-02-23⁩ → ⁦2028-05-02⁩Float: ⁦0⁩d+123
Final handoverPlanned: ⁦2027-12-31⁩ → ⁦2027-12-31⁩Forecast: ⁦2028-05-02⁩ → ⁦2028-05-02⁩Float: ⁦0⁩dFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦21⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦15⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦10⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.

The critical chain

In date order, to final acceptance