DMD-2026-009

Multi-storey car park for the Riyadh court campus, with a private partner

Initial reviewProposal
Priority score
58

Preliminary score from screening — confirmed after evaluation

Estimated cost
SAR 120M
Net present value
—

After the business case

Internal rate of return
—

After the business case

Payback period
—

After the business case

Rank in the 2027 plan
—
  1. Gate into «Submitted»DecisionGoDate9 August 2026DraftComplete
  2. Gate into «Initial review»DecisionGoDate16 August 2026SubmittedComplete
  3. Gate into «Feasibility»DecisionNot held yetInitial reviewCurrent phaseCurrent phase
  4. Gate into «Evaluation»DecisionNot held yet4FeasibilityNot started
  5. Gate into «Committee review»DecisionNot held yet5EvaluationNot started
  6. Gate into «Approved»DecisionNot held yet6Committee reviewNot started
  7. Gate into «Prioritized»DecisionNot held yet7ApprovedNot started
  8. Gate into «Converted to project»DecisionNot held yet8PrioritizedNot started
  9. 9Converted to projectNot started

The request as filed

What the requester wrote on the intake form

Problem
The Riyadh HQ and administrative court are short of an estimated 2,300 parking spaces during hearing hours, so litigants and lawyers arrive late for their hearings.
Current state
Parking occupancy is 118% at peak, and 25% of late arrivals at in-person hearings are down to looking for a space.
Objective
Three smart multi-storey car parks under a build-operate-transfer partnership with a private operator.
Expected scope
Design, build and operation through a partnership, smart guidance, and advance booking tied to the hearing time.

Expected benefits

Revenue

An estimated SAR 6M a year in concession revenue

Time & speed

Time spent looking for parking down 70%

Related lessons learned

From similar past projects (§78) — read them before evaluation

Settle the funding model before the tender

From Energy Retrofit of Existing Court Buildings (ESCO)

The Executive Committee put it on hold because the savings-repayment mechanism was not cleared by the Ministry of Finance.

Recommendation: For partnership or savings-funded requests, attach an in-principle finance approval before committee review.

Open the lesson

Confirm the land before approving the project

From Digital Administrative Court HQ, Wadi Al-Dawasir

The project was approved before the land was handed over by the municipality, and stopped after design award.

Recommendation: Do not pass a construction request to committee without a deed or final allocation letter.

Open the lesson