Board of GrievancesMunjaz10My actionsNotifications

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
83

In later requests and projects

High impact
10

Cost days or millions

In review
2

Waiting for EPMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Procurement

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 70Same project typeFits its phase
  3. 70Same project typeFits its phase
  4. 53Same project typeProven
  5. 45Same project type

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

Confirm the land before approving the project

LL-2026-033 · Land · High impact · Published

  1. 1ContextThe Digital Administrative Court HQ in Wadi Al-Dawasir.
  2. 2What happenedThe project was approved before the land was handed over by the municipality, and stopped after design award.
  3. 3ImpactA project on hold and a design contract idle.

Recommendation

Do not pass a construction request to committee without a deed or final allocation letter.

Captured by
Eng. Shahad M. Al-Malki
Date
2026-03-1930 Ramadan 1447 AH